Difference between revisions of "Controls Meeting 15-May-2014"
From GlueXWiki
(→Action items) |
|||
Line 22: | Line 22: | ||
= Action items = | = Action items = | ||
− | * Dave needs to implement alarms on the supply pressure | + | * Dave needs to implement alarms on the supply pressure. |
− | * Mike will implement some parameters that Dave can use to adjust the cycling of the pressure measurements | + | * Mike will implement some parameters that Dave can use to adjust the cycling of the pressure measurements. |
− | * Mike will find a way to turn the gas off without changing the set-point | + | * Mike will find a way to turn the gas off without changing the set-point (check if Brooks controllers allow the valve to be shut off). |
− | + | * <strike>Beni wants to have a bottle at the T to run gas into CDC, Dave will set it up. </strike> | |
− | * Beni wants to have a bottle at the T to run gas into CDC, Dave will set it up. | + | * <strike>Nerses and Vanik will finish the TOF voltages and start tagger hodoscope voltage controls. </strike> |
− | * Nerses and Vanik will finish the TOF voltages and start tagger hodoscope voltage controls | + |
Latest revision as of 10:25, 28 May 2014
Agenda
- Announcements
- Minutes from previous meeting Controls Meeting 1-May-2014
- Gas system control in PLC Media:FDC_Gas.pptx (Dave)
- EPICS GUIs for the gas system CDC/FDC_Gas_System_GUI(Mike)
- Status of TOF voltage controls (Nerses, Vanik)
- Any other business
Minutes
Present: Dave, Mike, Nerses, Vanik, Orlando, Beni, Elton
Gas System
- Dave showed details of the gas system controls for CDC and FDC.
- Mike presented his EPICS GUIs for gas system control.
TOF voltages
- Vanik and Nerses are working on TOF voltage controls.
- Vanik showed preliminary control screens for TOF voltages.
Action items
- Dave needs to implement alarms on the supply pressure.
- Mike will implement some parameters that Dave can use to adjust the cycling of the pressure measurements.
- Mike will find a way to turn the gas off without changing the set-point (check if Brooks controllers allow the valve to be shut off).
-
Beni wants to have a bottle at the T to run gas into CDC, Dave will set it up. -
Nerses and Vanik will finish the TOF voltages and start tagger hodoscope voltage controls.