= Minutes = | = Minutes = | ||
− | Participants: Eugene | + | Participants: Eugene, Dave, Chris, Nick, Beni, and Lubomir. |
== Production == | == Production == | ||
− | - Dave for the spare parts: | + | - Dave for the spare parts: |
- Lubomir for package #2: completely tested, oxygen went down to 170ppm. Started installing the grounding, 75% done. It is now on the mounting table | - Lubomir for package #2: completely tested, oxygen went down to 170ppm. Started installing the grounding, 75% done. It is now on the mounting table |
Revision as of 16:48, 28 February 2013
February 28, 2013 FDC meeting
Agenda
- Production Construction Tracking (Dave)
- Spare parts
- Spare wire plane testing
- Package #2 status
- Rebaselining update [1](Lubomir)
- Engineering (Bill)
- Cooling system test
- Electronics (Chris, Nick)
- Tests at EEL126 FDC E-log (Beni)
- Other