# Progress on UConn construction contract -- ''Richard'' | # Progress on UConn construction contract -- ''Richard'' | ||
#* July 3 -- Solicitation received at UConn ! | #* July 3 -- Solicitation received at UConn ! | ||
− | #* July | + | #* July 20 -- Response from UConn to solicitation |
# [http://zeus.phys.uconn.edu/halld/tagger/lowcurrent-7-2012/Photon-Flux-Gan.pptx Requirements for low current operation] -- ''Liping'' | # [http://zeus.phys.uconn.edu/halld/tagger/lowcurrent-7-2012/Photon-Flux-Gan.pptx Requirements for low current operation] -- ''Liping'' | ||
# Study of the fixed tagger array geometry -- ''Dan'' | # Study of the fixed tagger array geometry -- ''Dan'' |
Revision as of 11:38, 9 July 2012
- Time: 11:30 EST
- Place: ESNET and EVO (with telephone bridge id 555 2690)
- Connecting: instructions are here
- Present: Mike D., Barry R., Dan S., Franz K., Alex S., Tim W., Yi Q., Curtis M., Richard J., Igor S., Brendan P., Fridah M., James M., and Alex B.
Agenda
- Announcements
- Progress on UConn construction contract -- Richard
- July 3 -- Solicitation received at UConn !
- July 20 -- Response from UConn to solicitation
- Requirements for low current operation -- Liping
- Study of the fixed tagger array geometry -- Dan
- Report from Glasgow group -- Ken
- Report from ASU group -- Mike
- Update on microscope construction -- James
- possible loan of DAq system with FADC to UConn
- possible swap of two SIPM's with Jlab (soon??)