Line 5: | Line 5: | ||
# Production [http://www.jlab.org/Hall-D/detector/fdc/production/FDC_Construction_Tracking_July28.xlsx Construction Tracking] (Dave) | # Production [http://www.jlab.org/Hall-D/detector/fdc/production/FDC_Construction_Tracking_July28.xlsx Construction Tracking] (Dave) | ||
#* Status | #* Status | ||
− | #* Wire deadening [http://www.jlab.org/Hall-D/detector/fdc/procedures/fdc_calculations4. | + | #* Wire deadening [http://www.jlab.org/Hall-D/detector/fdc/procedures/fdc_calculations4.xlsx Bill's calculations] |
#* Leakage current tests (Lubomir) | #* Leakage current tests (Lubomir) | ||
#* Revised short term production [http://www.jlab.org/Hall-D/detector/fdc/procedures/REVISION_FDC_START_PRODUCTION.jpg schedule] (Lubomir) | #* Revised short term production [http://www.jlab.org/Hall-D/detector/fdc/procedures/REVISION_FDC_START_PRODUCTION.jpg schedule] (Lubomir) |
Revision as of 15:44, 28 July 2011
July 28, 2011 FDC meeting
Agenda
- Production Construction Tracking (Dave)
- Status
- Wire deadening Bill's calculations
- Leakage current tests (Lubomir)
- Revised short term production schedule (Lubomir)
- Engineering update (Bill)
- Electronics update (Chris)
- Chamber testing at EEL126 (Beni)
- Status and plans efficiency plot
- Other