** do we need to add or change anything?
 
** do we need to add or change anything?
 
* Coil 2 status
 
* Coil 2 status
** installation and cooldown timeline
+
** installation status
** coil inductances and quench detector
+
** hi-pot results
 +
** cooldown timeline
 +
** subcoil inductances and quench detector
 
** Danfysik fault sequencer and slow dump
 
** Danfysik fault sequencer and slow dump
 
** additional PLC and HMI programming
 
** additional PLC and HMI programming

Revision as of 16:56, 7 June 2011

Solenoid Coil Test Weekly Meeting

Location and Time

  • Fri 10-Jun-2011 9:30 am ARC 231


Agenda

  • Lessons learned from Coil 3
    • do we need to add or change anything?
  • Coil 2 status
    • installation status
    • hi-pot results
    • cooldown timeline
    • subcoil inductances and quench detector
    • Danfysik fault sequencer and slow dump
    • additional PLC and HMI programming
    • fast DAQ
    • anything else?
  • Documentation
    • trip chains
    • anything else?
  • Will there be any auxiliary tests?
  • To-do list for the next coil
    • measure UPS lifetime under operating conditions
  • IRMIS at JLab
    • filled with BNL "training" data
  • Preparing for moving into the hall
    • order all controls equipment so P6 line can be closed