Difference between revisions of "Coil Test Weekly Meeting 10-Jun-2011"
From GlueXWiki
m |
|||
Line 10: | Line 10: | ||
* Lessons learned from Coil 3 | * Lessons learned from Coil 3 | ||
− | ** | + | ** do we need to add or change anything? |
* Coil 2 status | * Coil 2 status | ||
** installation and cooldown timeline | ** installation and cooldown timeline | ||
Line 20: | Line 20: | ||
* Documentation | * Documentation | ||
** trip chains | ** trip chains | ||
− | ** anything else | + | ** anything else? |
* Will there be any auxiliary tests? | * Will there be any auxiliary tests? | ||
* [[For_the_fourth_coil|To-do list]] for the next coil | * [[For_the_fourth_coil|To-do list]] for the next coil |
Revision as of 16:53, 7 June 2011
Solenoid Coil Test Weekly Meeting
Location and Time
- Fri 10-Jun-2011 9:30 am ARC 231
Agenda
- Lessons learned from Coil 3
- do we need to add or change anything?
- Coil 2 status
- installation and cooldown timeline
- coil inductances and quench detector
- Danfysik fault sequencer and slow dump
- additional PLC and HMI programming
- fast DAQ
- anything else?
- Documentation
- trip chains
- anything else?
- Will there be any auxiliary tests?
- To-do list for the next coil
- measure UPS lifetime under operating conditions
- IRMIS at JLab
- filled with BNL "training" data
- Preparing for moving into the hall