Difference between revisions of "Coil Test Weekly Meeting 3-Dec-2010"
From GlueXWiki
m |
|||
Line 10: | Line 10: | ||
'''Agenda''' | '''Agenda''' | ||
− | * Do we want | + | * Do we want to install a second quench detector - Mark, Elliott |
− | * Cryogenic operations experience - | + | * Cryogenic operations experience - All |
− | ** | + | ** vapor-cooled lead blockage |
− | ** | + | ** document our experience |
+ | ** additions to HMI and EWEB pages | ||
− | * | + | * Status of preparation for powered operations - All |
− | ** shunt | + | ** shunt for fast and slow dump |
− | + | ** fast DAQ | |
− | ** fast DAQ | + | ** sweep, signage, etc. |
− | ** | + | |
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
** UPS lifetime test | ** UPS lifetime test | ||
− | |||
− | |||
− | |||
** alarm system | ** alarm system | ||
− | ** | + | ** paging system and guard shack |
− | ** | + | ** HMI status, archives, etc. |
+ | ** second HMI computer | ||
− | * | + | * Status of 230 V UPS on Danfysik control boards, main switch - Elliott |
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
* Elog - Elliott | * Elog - Elliott | ||
Line 65: | Line 36: | ||
** coil 2 winding supports | ** coil 2 winding supports | ||
** plans for coil 4 | ** plans for coil 4 | ||
− | |||
− | |||
* PI Responsibilities during test - Jonathan | * PI Responsibilities during test - Jonathan | ||
Line 87: | Line 56: | ||
** quench detector | ** quench detector | ||
** connectors | ** connectors | ||
− | + | ** what else might be useful? | |
− | ** what else? | + |
Latest revision as of 14:32, 2 December 2010
Solenoid Coil Test Weekly Meeting
Location and Time
Note new meeting day
- Fri 3-Dec-2010 9:30 am ARC 428
Agenda
- Do we want to install a second quench detector - Mark, Elliott
- Cryogenic operations experience - All
- vapor-cooled lead blockage
- document our experience
- additions to HMI and EWEB pages
- Status of preparation for powered operations - All
- shunt for fast and slow dump
- fast DAQ
- sweep, signage, etc.
- UPS lifetime test
- alarm system
- paging system and guard shack
- HMI status, archives, etc.
- second HMI computer
- Status of 230 V UPS on Danfysik control boards, main switch - Elliott
- Elog - Elliott
- automatic entries
- Coil repair status - George
- coil 3 at IUCO
- coil 2 winding supports
- plans for coil 4
- PI Responsibilities during test - Jonathan
- Low power magnet testing 5A, 50A,100A - Elliott
- High power magnet testing 100-1500A - Elliott
- Identify possible turn to turn shorts during ramping - Eugene
- Assess Heim column centering in coil - George
- Assess Axial column forces - George
- Estimate LN2 and He heat leak - Jonathan
- Assess LN2 and LHe thermal siphons - Jonathan
- Preparations for testing next coil - George, Scot, Elliott
- ship coil 3 to JLab
- update P&I
- splices
- yoke location
- piping adaptors
- downstream yoke spacers
- controls racks rewiring
- quench detector
- connectors
- what else might be useful?