# Fcal | # Fcal | ||
− | #* Need to discuss strategy for fabrication of boards. Paul is concerned primarily about the HV board. We should include Fernando and Chris on the discussion for suggestion of production. | + | #* <strike> Need to discuss strategy for fabrication of boards. Paul is concerned primarily about the HV board. We should include Fernando and Chris on the discussion for suggestion of production.</strike> |
#* <strike> CR to modify schedules for new activities, including Fcal calibration. Elton to send proposal to listserver for comments. </strike> | #* <strike> CR to modify schedules for new activities, including Fcal calibration. Elton to send proposal to listserver for comments. </strike> | ||
# Bcal | # Bcal | ||
Line 16: | Line 16: | ||
#* Decide on a strategy for how to use fibers with slightly different systematics into matrix construction (e.g. randomizing them in the matrix). (everyone) | #* Decide on a strategy for how to use fibers with slightly different systematics into matrix construction (e.g. randomizing them in the matrix). (everyone) | ||
# Bcal readout | # Bcal readout | ||
− | #* Review decision on the orientation of FM pmt relative to Bfield, including tolerances due to expected field changes. (Elton, Will, Alam, Pedro) | + | #* <strike> Review decision on the orientation of FM pmt relative to Bfield, including tolerances due to expected field changes. (Elton, Will, Alam, Pedro) </strike> |
#* <strike> Alam will see if Pedro can generate new orientations of the pmts at an angle of 15 deg relative to the B field. </strike> | #* <strike> Alam will see if Pedro can generate new orientations of the pmts at an angle of 15 deg relative to the B field. </strike> | ||
#* Should order prototype light guides for typical configurations | #* Should order prototype light guides for typical configurations | ||
Line 40: | Line 40: | ||
Attendees: | Attendees: | ||
+ | |||
+ | # Announcements | ||
+ | # Review of Action Items | ||
+ | # Calibration/Monitoring | ||
+ | # Fcal | ||
+ | # Bcal | ||
+ | #* Status of construction / Readiness Review Schedule | ||
+ | #* Fibre QA: Shipments 1-5 ([http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1366 GlueX-doc-1366]) | ||
+ | # BCAL Readout | ||
+ | #* SiPM testing (Carl and Fernando) | ||
+ | #* New geometry for light guides (Alam/Pedro) | ||
+ | #* Light guide prototypes. See [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1365# Quote from Plastic Craft] and [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1367 Ray tracing through light guides] | ||
+ | # Other business |
Revision as of 17:45, 15 October 2009
Teleconference Time: 11:00 a.m. EST
- ESNET and EVO session
- Phone only if requested:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 77438230# (remember the "#"). Phone line by request only.
Contents
Items for followup from previous meeting(s)
- Fcal
-
Need to discuss strategy for fabrication of boards. Paul is concerned primarily about the HV board. We should include Fernando and Chris on the discussion for suggestion of production. -
CR to modify schedules for new activities, including Fcal calibration. Elton to send proposal to listserver for comments.
-
- Bcal
- Web page needs to be setup for communications.
- Decide on a strategy for how to use fibers with slightly different systematics into matrix construction (e.g. randomizing them in the matrix). (everyone)
- Bcal readout
-
Review decision on the orientation of FM pmt relative to Bfield, including tolerances due to expected field changes. (Elton, Will, Alam, Pedro) -
Alam will see if Pedro can generate new orientations of the pmts at an angle of 15 deg relative to the B field. - Should order prototype light guides for typical configurations
-
Documents to Review
Tentative Agenda
- Announcements
- Review of Action Items
- Calibration/Monitoring
- Fcal
- Bcal
- Status of construction / Readiness Review Schedule
- Fibre QA: Shipments 1-5 (GlueX-doc-1366)
- BCAL Readout
- SiPM testing (Carl and Fernando)
- New geometry for light guides (Alam/Pedro)
- Light guide prototypes. See Quote from Plastic Craft and Ray tracing through light guides
- Other business
Minutes
Attendees:
- Announcements
- Review of Action Items
- Calibration/Monitoring
- Fcal
- Bcal
- Status of construction / Readiness Review Schedule
- Fibre QA: Shipments 1-5 (GlueX-doc-1366)
- BCAL Readout
- SiPM testing (Carl and Fernando)
- New geometry for light guides (Alam/Pedro)
- Light guide prototypes. See Quote from Plastic Craft and Ray tracing through light guides
- Other business