Difference between revisions of "Hall-B Schedule"
From GlueXWiki
Line 1: | Line 1: | ||
''All travel, shipping and task schedule information, in connection to the BCAL beam tests at Hall-B (Sep. 2006) is kept on this page.'' | ''All travel, shipping and task schedule information, in connection to the BCAL beam tests at Hall-B (Sep. 2006) is kept on this page.'' | ||
+ | |||
+ | |||
+ | ''Tentative dates for Regina personnel:'' | ||
+ | |||
+ | Rafael (Aug. 20 - Oct. 5), Blake (Aug 20. - Oct. 5), Zisis (Aug. 20 - Aug. 27, Sep. 20 - Oct. 1), Ioanna (Sep. 20 - Oct. 1), George (Sep. 22 - Oct. 1), Garth (Sep. 22 - Oct. 1) | ||
'''The Table below shows the GlueX-related items from the most recent Hall-B schedule.''' | '''The Table below shows the GlueX-related items from the most recent Hall-B schedule.''' | ||
+ | |||
+ | Earliest occupancy: August 16, targeted occupancy: August 22. | ||
Revision as of 16:26, 6 July 2006
All travel, shipping and task schedule information, in connection to the BCAL beam tests at Hall-B (Sep. 2006) is kept on this page.
Tentative dates for Regina personnel:
Rafael (Aug. 20 - Oct. 5), Blake (Aug 20. - Oct. 5), Zisis (Aug. 20 - Aug. 27, Sep. 20 - Oct. 1), Ioanna (Sep. 20 - Oct. 1), George (Sep. 22 - Oct. 1), Garth (Sep. 22 - Oct. 1)
The Table below shows the GlueX-related items from the most recent Hall-B schedule.
Earliest occupancy: August 16, targeted occupancy: August 22.
ID | Task Name | Work | Duration | Start | Finish | % Work Complete |
---|---|---|---|---|---|---|
151 | GlueX calorimeter | 196 hrs | 9.5 days | Thu 8/3/06 | Wed 8/16/06 | 0% |
152 | Install calorimeter stand | 72 hrs | 3 days | Thu 8/3/06 | Mon 8/7/06 | 0% |
3 | Doug | 24 hrs | Thu 8/3/06 | Mon 8/7/06 | 0% | |
4 | Calvin | 24 hrs | Thu 8/3/06 | Mon 8/7/06 | 0% | |
10 | Crane | 24 hrs | Thu 8/3/06 | Mon 8/7/06 | 0% | |
153 | Install Bcal support | 0 hrs | 1 day | Tue 8/8/06 | Tue 8/8/06 | 0% |
154 | Install calorimeter | 120 hrs | 5 days | Wed 8/9/06 | Tue 8/15/06 | 0% |
3 | Doug | 40 hrs | Wed 8/9/06 | Tue 8/15/06 | 0% | |
4 | Calvin | 40 hrs | Wed 8/9/06 | Tue 8/15/06 | 0% | |
10 | Crane | 40 hrs | Wed 8/9/06 | Tue 8/15/06 | 0% | |
155 | Install Down Stream Helium Bag | 4 hrs | 4 hrs | Wed 8/16/06 | Wed 8/16/06 | 0% |
2 | Steve | 4 hrs | Wed 8/16/06 | Wed 8/16/06 | 0% | |
156 | SURVEY | 44 hrs | 15.63 days | Thu 7/27/06 | Thu 8/17/06 | 0% |
157 | Survey Frascati magnets | 8 hrs | 8 hrs | Tue 8/8/06 | Tue 8/8/06 | 0% |
12 | Survey | 8 hrs | Tue 8/8/06 | Tue 8/8/06 | 0% | |
158 | Survey Pair Spectrometer | 8 hrs | 1 day | Wed 8/9/06 | Wed 8/9/06 | 0% |
12 | Survey | 8 hrs | Wed 8/9/06 | Wed 8/9/06 | 0% | |
159 | Survey GlueX calorimeter | 8 hrs | 1 day | Wed 8/16/06 | Thu 8/17/06 | 0% |
12 | Survey | 8 hrs | Wed 8/16/06 | Thu 8/17/06 | 0% | |
160 | Survey Target | 8 hrs | 1 day | Thu 7/27/06 | Fri 7/28/06 | 0% |
12 | Survey | 8 hrs | Thu 7/27/06 | Fri 7/28/06 | 0% |