Line 15: | Line 15: | ||
* Get magnetic field map for single coil, no cladding, fine scale - George, Floyd | * Get magnetic field map for single coil, no cladding, fine scale - George, Floyd | ||
* Get overall system diagram and controls strategy for Mark Wissman - George | * Get overall system diagram and controls strategy for Mark Wissman - George | ||
+ | * Begin design and programming of PLC controls software - Mark W | ||
* Order controls equipment - Mark S and Elliott | * Order controls equipment - Mark S and Elliott | ||
* Order platform components - George | * Order platform components - George | ||
Line 160: | Line 161: | ||
* '''To Do:''' | * '''To Do:''' | ||
− | ** | + | ** Explain overall control strategy to Mark W - George |
** Purchase new software licenses - Elliott | ** Purchase new software licenses - Elliott | ||
** Install all software on controls computer - Mark W | ** Install all software on controls computer - Mark W | ||
** Borrow code from Steve Lassiter - Mark W | ** Borrow code from Steve Lassiter - Mark W | ||
− | |||
** Determine what needs to be archived and how often - George | ** Determine what needs to be archived and how often - George | ||
** Set up controls hardware in Mark W's office - Mark W and Elliott | ** Set up controls hardware in Mark W's office - Mark W and Elliott | ||
Line 171: | Line 171: | ||
* Done | * Done | ||
− | + | ** Install new memory in controls computer - Elliott and Mark W - done 6-Jul-2009 | |
===Staging=== | ===Staging=== |
Revision as of 15:06, 6 July 2009
Notes and To-Do lists for the solenoid coil tests this summer and fall.
Contents
Meetings
Top To-Do Items
- Complete coil repair work - Kevin
- Order cryo can and related components - George
- Complete platform design and area layout - Wayne
- Get magnetic field map for single coil, no cladding, fine scale - George, Floyd
- Get overall system diagram and controls strategy for Mark Wissman - George
- Begin design and programming of PLC controls software - Mark W
- Order controls equipment - Mark S and Elliott
- Order platform components - George
- Arrange for piping designer - George, Tim
Test Area
- Notes:
- Area in the test lab is 20'6" x 25'9", currently filled with coils and coil parts.
- Bob Bennett is Test Lab "space czar."
- Wayne is designing overall layout.
- Will use SRF storage area for large power supply (6' x 5', 5' H, 5000 lbs) and switch (QWeak area unavailable).
- Must maintain clear areas around racks and power supply, and cannot block pedestrian walkways.
- Platform is 172" x 160", cryo can will sit on top.
- Platform must be removed to swap coils, and all connections to it must be broken.
- Area has two 25T cranes, but need both (and spreader bar) to lift heaviest yoke (45 tons).
- Need come-alongs and anchors to move yokes and coils along rails.
- Some areas will need to be roped off due to high B fields (5 G for pacemakers; other limits 60 G 8-hr body, 600 G 8-hr limb).
- May need to remove some fences.
- Magnet forces: 5 kG == 1 Atm, scales as square of B field.
- To Do:
- Look into possibility of locating computer in control room (contact Joe Preble, Mark Drury)- Elliott
- Distribute Floyd's B field map for single coil, no cladding, fine scale - George
- Determine location of all components - Wayne
- Investigate sensitivity of electronic equipment to B fields - Elliott
- Find spreader bar - George
- Determine areas to be roped off due to high B field - George, Elliott
- Prepare area for installation - Mark S, others
- Done
- Enable building access for everyone - Elliott - done 19-Jun-2009 (same requirements as access to Cebaf Center)
- Look into getting space in adjacent areas - George - done 2-Jul-2009
Infrastructure
- Notes:
- Platform borrowed from Hall A.
- Must be moved to replace coils, 4-point lift.
- Rails currently at IU.
- Have or can borrow all material moving equipment, or will contract out to rigging firm.
- Have or can borrow all tools needed.
- Controls racks coming from Randy H or from computer center.
- Need 60 W liquid He, Test Lab supply capable of 500 W, but share with Cryo group.
- Must account for magnetic forces on all structures, perhaps as much as 20-30 Gauss static B field.
- Need support for heat exchanger.
- Electrical cables must be untouchable to 8 feet above floor.
- To Do:
- Produce overall system diagram - George
- Design structures and mechanical components, route cables and piping, etc. - Wayne
- Arrange for piping designer - George
- Design piping to vent N2.
- Design warm and cold He supply/return systems, LN2 supply system.
- Determine if any ODH considerations for N2 vent.
- Retrieve rails from IU - George and Elliott
- Get three racks from Randy H or from CC - Mark S and Elliott W
- Determine cryogen supply/return needs - George
- Arrange for cryogen supply/return with Dana Arenius (and Kelly Dixon?)- George and Elliott
- Find or order electrical switch and cables - Mark S
- Arrange for electrical infrastructure intallation - Mark S and Elliott
- Get heat exchanger support - Mark S
- Done
Components
- Platform
- Entire platform and supports will be moved when changing coils.
- Must account for magnetic forces.
- Ladder needs to be shortened and straightened.
- Must include cable trays and strain relief, especially for power connections.
- Rails
- Currently in transportainer at IU, George will have a look when he goes out there.
- Cryo can and heat exchanger
- RFQ out for cryo can, no delivery date yet.
- Heat exchanger from Hall A.
- Piping
- Not clear where N2 vent will be routed.
- Must incorporate drip pan under N2 vent due to icing.
- May be ODH considerations.
- Electrical power
- Need to work out where outlets are needed.
- Power supply
- Resides in Phsyics Storage bldg.
- Uses 3-phase 480 V.
- 10V supply (5 V?)
- Integral dump resistor.
- Need switch nearby.
- Cables not water-cooled. 1.5" diameter cables, 1" copper.
- Coils and yokes
- Are yoke modifications are needed?
- Coil repairs will continue through summer 2009.
- All must be leak-tested again.
- Controls system
- Is anything sensitive to B fields?
- Will wire up as per final four-coil system.
- Should we go with separate chassis for each coil?
- Own DIN-mount RS232 module, can borrow power supply and ControlNet module from Steve L.
- Steve L has cable and terminators, may need T-taps.
- Not clear where computer will be located.
- Misc tools, tables, chairs, ladders, etc.
- What do we need? Can we beg, borrow, and/or steal?
- To Do:
- Complete JLab and IUCF coil repairs - George
- Understand how to deal with dump resistor in power supply - Mark S
- Order cryo can - George
- Verify all cryo transfer lines and U-tubes are available on site - Mark S and George
- Order remaining piping - ?
- Design cryo and electrical break system for cryo can - George and Mark S
- Arrange for yoke modifications if needed - George
- Determine if sensible to use one PLC chassis per coil - Mark S and Elliott
- Get heat exchanger - Mark S
- Ensure we have all tools needed - Mark S and Elliott
- Done
- Verify we can borrow heat exchanger from Hall A - Mark S - done 2-Jul-2009
Programming
- Notes:
- Mark W will do all programming.
- Can borrow lots of code from Steve Lassiter and co.
- Single computer will perform all control and monitoring tasks.
- To Do:
- Explain overall control strategy to Mark W - George
- Purchase new software licenses - Elliott
- Install all software on controls computer - Mark W
- Borrow code from Steve Lassiter - Mark W
- Determine what needs to be archived and how often - George
- Set up controls hardware in Mark W's office - Mark W and Elliott
- Design and implement full control and archiving system - Mark W
- Done
- Install new memory in controls computer - Elliott and Mark W - done 6-Jul-2009
Staging
- Notes:
- Will instrument controls racks in F117, then move to Test Lab.
- Will instrument for final 4-coil system.
- To Do:
- Rearrange F117 - Mark S and Beni
- Get and move 3 racks into F117 - Mark S
- Verify adequate staging areas available in Test Lab - Mark S and Elliott
- Done
Reviews
- Notes:
- Bob May and Paul Collins are contacts with EHS&Q for safety documentation and reviews
- Need cryo, electrical, mechanical, and operations reviews.
- Suresh Chandra will (internally) review structural aspects of the new platform and related components.
- There will be a DOE (I think) magnet review on Oct 2009.
- To Do:
- Write appropriate documentation - George, Mark S, Wayne and Elliott
- Set up all reviews - George and Elliott
- Done
- Mini-review of PLC vendor choice (Report from Omar Garza and Jonathan Creel) - done 15-Jun-2009
- Write thank-you letter to Jonathan Creel and Omar Garza for participating in PLC vendor review - Elliott - done 24-Jun-2009
- Contact EH&S group concerning documentation and reviews - Elliott - done 29-Jun-2009
Construction
- Notes:
- Do we have enough manpower?
- What training do we all need?
- To Do:
- Get appropriate training - All
- Arrange for any coil or yoke modifications - George
- Order controls equipment - Mark S and Elliott
- Arrange for telephone and networking in test area - Elliott
- Arrange for installation of electrical infrastructure - Mark S
- Wire up controls racks - Mark S
- Move controls racks to Test Lab - Mark S
- Move computer to Test Lab - Mark W and Elliott
- Install all components - Mark S
- Hook up controls system - Mark S, Mark W and Elliott
- Verify operation of control/archiving system - Mark W, Mark S, George and Elliott
- Done
Coil Tests
- Notes:
- Purpose:
- Verify correct operation of all coils.
- Measure coil strains up to full current (1600 A).
- Will take about one month per coil.
- Will take a few days to cool down a single coil (warm up?).
- Purpose:
- To Do:
- Create test plan - George
- Done