Difference between revisions of "Solenoid Coil Test in Test Lab"
From GlueXWiki
m |
m |
||
Line 7: | Line 7: | ||
** Wayne is designing overall layout. | ** Wayne is designing overall layout. | ||
** Area in the test lab is 20'6" x 25'9", currently filled with coils and coil parts. | ** Area in the test lab is 20'6" x 25'9", currently filled with coils and coil parts. | ||
+ | ** Bob Bennett is Test Lab "space czar." | ||
** May be able to get space in adjacent areas (QWeak construction and SRF cavity storage areas). | ** May be able to get space in adjacent areas (QWeak construction and SRF cavity storage areas). | ||
− | ** May need extra space for large power supply (6' x 5') and switch, and to avoid placing controls racks in large B field. | + | ** May need extra space for large power supply (6' x 5', 5' H, 5000 lbs) and switch, and to avoid placing controls racks in large B field. |
** Must maintain clear areas around racks and power supply, and cannot block pedestrian walkways. | ** Must maintain clear areas around racks and power supply, and cannot block pedestrian walkways. | ||
** Platform is 172" x 160", cryo can will sit on top. | ** Platform is 172" x 160", cryo can will sit on top. | ||
** Platform must be removed to swap coils, and all connections to it must be broken. | ** Platform must be removed to swap coils, and all connections to it must be broken. | ||
− | ** Area has two cranes, but need both (and spreader bar) to lift heaviest yoke (45 tons). | + | ** Area has two 25T cranes, but need both (and spreader bar) to lift heaviest yoke (45 tons). |
** Need come-alongs and anchors to move yokes and coils along rails. | ** Need come-alongs and anchors to move yokes and coils along rails. | ||
** Some areas will need to be roped off due to high B fields (> 5 Gauss, for pacemakers) | ** Some areas will need to be roped off due to high B fields (> 5 Gauss, for pacemakers) | ||
+ | ** May need to remove some fences. | ||
* '''To Do:''' | * '''To Do:''' | ||
** Look into getting space in adjacent areas - George | ** Look into getting space in adjacent areas - George | ||
− | ** Look into possibility of locating computer in control room - Elliott | + | ** Look into possibility of locating computer in control room (contact Joe Preble, Mark Drury)- Elliott |
** Distribute Floyd's B field map for single coil, no cladding - George | ** Distribute Floyd's B field map for single coil, no cladding - George | ||
** Determine location of all components - Wayne | ** Determine location of all components - Wayne | ||
Line 35: | Line 37: | ||
** Have or can borrow all tools needed. | ** Have or can borrow all tools needed. | ||
** Controls racks coming from Randy H or from computer center. | ** Controls racks coming from Randy H or from computer center. | ||
+ | ** Need 60 W liquid He, Test Lab supply capable of 500 W, but share with Cryo group. | ||
+ | ** Must account for magnetic forces on all structures, perhaps as much as 20-30 Gauss static B field. | ||
* '''To Do:''' | * '''To Do:''' | ||
** Produce overall system diagram - George | ** Produce overall system diagram - George | ||
− | ** Design structures and mechanical components, route cables and | + | ** Design structures and mechanical components, route cables and piping, etc. - Wayne |
** Arrange for piping designer - George | ** Arrange for piping designer - George | ||
*** Design piping to vent N2. | *** Design piping to vent N2. | ||
Line 51: | Line 55: | ||
===Components=== | ===Components=== | ||
− | * | + | * Platform |
+ | * Rails | ||
+ | * Cryo can and heat exchanger | ||
+ | * Piping | ||
+ | * Electrical power | ||
+ | * Power supply | ||
+ | * Coils and yokes | ||
+ | * Controls system | ||
+ | * Misc: tools, tables and chairs, ladders, etc. | ||
* '''To Do:''' | * '''To Do:''' | ||
+ | ** Understand how to deal with dump resistor in power supply - Mark S | ||
** Order cryo can - George | ** Order cryo can - George | ||
− | ** Verify all cryo transfer lines and U-tubes are available on site - Mark S | + | ** Verify all cryo transfer lines and U-tubes are available on site - Mark S and George |
** Verify we can borrow heat exchanger from Hall A - George | ** Verify we can borrow heat exchanger from Hall A - George | ||
** Get heat exchanger - Mark S | ** Get heat exchanger - Mark S | ||
** Order remaining piping - ? | ** Order remaining piping - ? | ||
+ | ** Design cryo and electrical/electronics break system - George and Mark S | ||
Line 73: | Line 87: | ||
** Install all software on controls computer - Mark W | ** Install all software on controls computer - Mark W | ||
** Borrow code from Steve Lassiter - Mark W | ** Borrow code from Steve Lassiter - Mark W | ||
− | ** | + | ** Explain overall control strategy to Mark W - George |
+ | ** Determine what needs to be archived and how often - George | ||
+ | ** Design and implement full control and archiving system - Mark W | ||
Line 107: | Line 123: | ||
* '''To Do:''' | * '''To Do:''' | ||
+ | ** Arrange for any coil or yoke modifications - George | ||
+ | ** Order controls equipment - Mark S and Elliott | ||
** Arrange for telephone and networking in test area - Elliott | ** Arrange for telephone and networking in test area - Elliott | ||
** Arrange for installation of electrical infrastructure - Mark S | ** Arrange for installation of electrical infrastructure - Mark S | ||
** Move controls racks to Test Lab - Mark S | ** Move controls racks to Test Lab - Mark S | ||
** Move computer to Test Lab - Mark W and Elliott | ** Move computer to Test Lab - Mark W and Elliott | ||
− | ** Install | + | ** Install all components - Mark S |
** Hook up controls system - Mark S, Mark W and Elliott | ** Hook up controls system - Mark S, Mark W and Elliott | ||
** Verify operation of control/archiving system - Mark W, Mark S, George and Elliott | ** Verify operation of control/archiving system - Mark W, Mark S, George and Elliott | ||
Line 118: | Line 136: | ||
===Coil Tests=== | ===Coil Tests=== | ||
− | * | + | * Purpose: |
** Verify correct operation of all coils. | ** Verify correct operation of all coils. | ||
** Determine stresses up to full current (1600 A). | ** Determine stresses up to full current (1600 A). | ||
Line 127: | Line 145: | ||
* To Do: | * To Do: | ||
** Create test plan - George | ** Create test plan - George | ||
− |
Revision as of 15:24, 18 June 2009
Notes and to-do lists for the solenoid coil tests this summer and fall.
Contents
Test Area
- Notes:
- Wayne is designing overall layout.
- Area in the test lab is 20'6" x 25'9", currently filled with coils and coil parts.
- Bob Bennett is Test Lab "space czar."
- May be able to get space in adjacent areas (QWeak construction and SRF cavity storage areas).
- May need extra space for large power supply (6' x 5', 5' H, 5000 lbs) and switch, and to avoid placing controls racks in large B field.
- Must maintain clear areas around racks and power supply, and cannot block pedestrian walkways.
- Platform is 172" x 160", cryo can will sit on top.
- Platform must be removed to swap coils, and all connections to it must be broken.
- Area has two 25T cranes, but need both (and spreader bar) to lift heaviest yoke (45 tons).
- Need come-alongs and anchors to move yokes and coils along rails.
- Some areas will need to be roped off due to high B fields (> 5 Gauss, for pacemakers)
- May need to remove some fences.
- To Do:
- Look into getting space in adjacent areas - George
- Look into possibility of locating computer in control room (contact Joe Preble, Mark Drury)- Elliott
- Distribute Floyd's B field map for single coil, no cladding - George
- Determine location of all components - Wayne
- Investigate sensitivity of electronic equipment to B fields - Elliott
- Find spreader bar - George
- Determine areas to be roped off due to high B field - Floyd, George
Infrastructure
- Notes:
- Platform borrowed from Hall A.
- Rails currently at IU.
- Have or can borrow all material moving equipment, or will contract out to rigging firm.
- Have or can borrow all tools needed.
- Controls racks coming from Randy H or from computer center.
- Need 60 W liquid He, Test Lab supply capable of 500 W, but share with Cryo group.
- Must account for magnetic forces on all structures, perhaps as much as 20-30 Gauss static B field.
- To Do:
- Produce overall system diagram - George
- Design structures and mechanical components, route cables and piping, etc. - Wayne
- Arrange for piping designer - George
- Design piping to vent N2.
- Design warm and cold He supply/return systems, LN2 supply system.
- Retrieve rails from IU - ?
- Get three racks from Randy H or from CC - Mark S and Elliott W
- Determine cryogen supply/return needs - George
- Arrange for cryogen supply/return with Dana Arenius (and Kelly Dixon?)- George and Elliott
Components
- Platform
- Rails
- Cryo can and heat exchanger
- Piping
- Electrical power
- Power supply
- Coils and yokes
- Controls system
- Misc: tools, tables and chairs, ladders, etc.
- To Do:
- Understand how to deal with dump resistor in power supply - Mark S
- Order cryo can - George
- Verify all cryo transfer lines and U-tubes are available on site - Mark S and George
- Verify we can borrow heat exchanger from Hall A - George
- Get heat exchanger - Mark S
- Order remaining piping - ?
- Design cryo and electrical/electronics break system - George and Mark S
Programming
- Notes:
- Mark W will do all programming.
- Can borrow lots of code from Steve Lassiter and co.
- Single computer will perform all control and monitoring tasks.
- To Do:
- Install new memory in controls computer - Elliott and Mark W
- Purchase new software licenses - Elliott
- Install all software on controls computer - Mark W
- Borrow code from Steve Lassiter - Mark W
- Explain overall control strategy to Mark W - George
- Determine what needs to be archived and how often - George
- Design and implement full control and archiving system - Mark W
Staging
- Notes:
- Will instrument controls racks in F117, then move to Test Lab.
- Will instrument for final 4-coil system.
- To Do:
- Rearrange F117 - Mark S and Beni
- Get and move 3 racks into F117 - Mark S
Reviews
- Notes:
- Micro-review of PLC vendor choice completed, waiting for report.
- Need cryo, electrical, mechanical, and operations reviews.
- To Do:
- Write thank-you letter to Jonathan Creel and Omar Garza for participating in PLC vendor review - Elliott
- Write appropriate documentation - George, Mark S, Wayne and Elliott
- Set up all reviews - George and Elliott
Construction
- Notes:
- Do we have enough manpower?
- To Do:
- Arrange for any coil or yoke modifications - George
- Order controls equipment - Mark S and Elliott
- Arrange for telephone and networking in test area - Elliott
- Arrange for installation of electrical infrastructure - Mark S
- Move controls racks to Test Lab - Mark S
- Move computer to Test Lab - Mark W and Elliott
- Install all components - Mark S
- Hook up controls system - Mark S, Mark W and Elliott
- Verify operation of control/archiving system - Mark W, Mark S, George and Elliott
Coil Tests
- Purpose:
- Verify correct operation of all coils.
- Determine stresses up to full current (1600 A).
- Will take about one month per coil.
- Will take a few days to cool down a single coil.
- To Do:
- Create test plan - George