Difference between revisions of "Solenoid Coil Test in Test Lab"
From GlueXWiki
m |
m |
||
Line 19: | Line 19: | ||
** Determine location of all components - Wayne | ** Determine location of all components - Wayne | ||
** Arrange for piping designer - George | ** Arrange for piping designer - George | ||
+ | ** Investigate sensitivity of electronic equipment to B fields - Elliott | ||
+ | |||
+ | ** Verify we have all cryo transfer lines and U-tubes - Mark S | ||
+ | ** Verify we can borrow heat exchanger from Hall A - George | ||
+ | ** Order warm He and N2 piping - ? | ||
Line 46: | Line 51: | ||
* Notes: | * Notes: | ||
+ | ** Micro-review of PLC vendor choice completed, waiting for report. | ||
* To Do: | * To Do: | ||
+ | ** Write thank-you letter to Jonathan Creel and Omar Garza for participating in PLC vendor review. |
Revision as of 13:51, 18 June 2009
Notes and to-do lists for the solenoid coil tests this summer and fall.
Test Area
- Notes:
- Area is in the test lab, footprint 20'6" x 25'9", currently filled with coils and coil parts.
- May be able to get space in adjacent area (QWeak construction and SRF cavity storage areas).
- Need space for large power supply (6' x 5') and to avoid placing controls racks in large B field.
- Must maintain clear areas around racks, power supply and cannot block pedestrian areas.
- Platform is 172" x 160".
- Need to design piping to vent N2.
- Need to design piping for warm and cold He, LN2.
- To Do:
- Look into getting space in adjacent areas - George
- Look into possibility of locating computer in control room - Elliott
- Distribute Floyd's B field map for single coil, no cladding - George
- Determine location of all components - Wayne
- Arrange for piping designer - George
- Investigate sensitivity of electronic equipment to B fields - Elliott
- Verify we have all cryo transfer lines and U-tubes - Mark S
- Verify we can borrow heat exchanger from Hall A - George
- Order warm He and N2 piping - ?
Infrastructure
- Notes:
- To Do:
Components
- Notes:
- To Do:
Staging
- Notes:
- To Do:
Reviews
- Notes:
- Micro-review of PLC vendor choice completed, waiting for report.
- To Do:
- Write thank-you letter to Jonathan Creel and Omar Garza for participating in PLC vendor review.