− | ''' | + | '''Preparation of parts for ECAL''' -- Sasha |
+ | :: -New LMS light source is ready [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/01_31_2025/lms_light_source.jpg]. Will be installed and checked during next week. Parts for holding reference PMTs are ready. | ||
+ | '''-Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All | ||
+ | * Implementing ECAL into the GlueX DAQ [https://logbooks.jlab.org/entry/4316928] | ||
+ | :: - Six VTPs have been installed, firmware loaded | ||
+ | :: - Testing GTP trigger using individual ECAL VXS crates [https://logbooks.jlab.org/entry/4327369] | ||
+ | *Commissioning the entire detector using the LMS (signal waveforms) | ||
+ | :: - Signal waveforms after resolving issues with the ECAL modules [https://logbooks.jlab.org/entry/4326773] | ||
+ | :: - Long-term stability check [https://logbooks.jlab.org/entry/4327882] | ||
+ | ::: [https://halldweb.jlab.org/wiki/index.php/List_of_ECAL_cosmic_runs List of cosmic runs] | ||
+ | * ECAL HV interlock check [https://logbooks.jlab.org/entry/4318704] | ||
+ | * HV module failed during cosmic run [https://logbooks.jlab.org/entry/4328335] | ||
+ | * Tuning HV settings [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/01_31_2025] | ||
+ | * Material in front of the ECAL, TOF absorber [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/01_24_2025/tof_abs1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/01_24_2025/tof_abs2.jpg] | ||
+ | * Temperature scan in the ECAL divider region [https://logbooks.jlab.org/entry/4320981][https://logbooks.jlab.org/entry/4321406][https://logbooks.jlab.org/entry/4321241] | ||
+ | :: Fans replaced in the central region [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/01_31_2025] | ||
+ | :: Lower detector high voltages [https://logbooks.jlab.org/entry/4327355] | ||
+ | :: [https://halldweb.jlab.org/detectors/fcal2/temperature/Temperature_Interpolation.pdf Temperature of the NPS detector][https://logbooks.jlab.org/entry/4327355] | ||
+ | :: 2 temperature sensors in the divider region connected, fan included into the detector interlock [https://logbooks.jlab.org/entry/4326362] -- Josh, Bobby | ||
+ | :: Temporary temperature sensors installed in the ECAL region [https://logbooks.jlab.org/entry/4329404] | ||
+ | * Preparing for the run -- Sasha | ||
+ | :: [https://halldweb.jlab.org/hdops/wiki/index.php/Electromagnetic_Calorimeter Page for shift Takers ] | ||
+ | :: [https://halldweb.jlab.org/detectors/fcal2/esad_safety ECAL in the Experimental Safety Assessment Document (ESAD)] | ||
+ | :: EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236) | ||
+ | * [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/safety.jpg Safety briefings] - Vlad, Sasha | ||
+ | * [https://halldweb.jlab.org/wiki/index.php/FCAL2_Meetings FCAL2 Engineering Meetings] | ||
+ | * [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
'''Restoring PS test setup''' [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/ps_setup.jpg] | '''Restoring PS test setup''' [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/ps_setup.jpg] | ||
− | + | :: Working on the plan for testing calorimeter prototype | |
''' [https://halldweb.jlab.org/wiki/index.php/ECAL_Commissioning ECAL commissioning]''' -- Sasha, All | ''' [https://halldweb.jlab.org/wiki/index.php/ECAL_Commissioning ECAL commissioning]''' -- Sasha, All | ||
Revision as of 10:19, 7 February 2025
Connection
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL -- Sasha
- -New LMS light source is ready [1]. Will be installed and checked during next week. Parts for holding reference PMTs are ready.
-Installation of the FCAL2 detector & integration to GlueX -- Sasha, All
- Implementing ECAL into the GlueX DAQ [2]
- - Six VTPs have been installed, firmware loaded
- - Testing GTP trigger using individual ECAL VXS crates [3]
- Commissioning the entire detector using the LMS (signal waveforms)
- ECAL HV interlock check [6]
- HV module failed during cosmic run [7]
- Tuning HV settings [8]
- Material in front of the ECAL, TOF absorber [9][10]
- Temperature scan in the ECAL divider region [11][12][13]
- Preparing for the run -- Sasha
- Page for shift Takers
- ECAL in the Experimental Safety Assessment Document (ESAD)
- EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236)
Restoring PS test setup [19]
- Working on the plan for testing calorimeter prototype
ECAL commissioning -- Sasha, All
Calibrations
Preparations for readiness review
- FCAL2 software -- Simon