Difference between revisions of "JEF meeting, November 15, 2024"
From GlueXWiki
(→Agenda) |
|||
Line 53: | Line 53: | ||
:: [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_08_2024 Update from Zhikun] | :: [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_08_2024 Update from Zhikun] | ||
<!-- :: [https://halldweb.jlab.org/DocDB/0066/006667/001/Update-Oct17.pdf Laveen Update] --> | <!-- :: [https://halldweb.jlab.org/DocDB/0066/006667/001/Update-Oct17.pdf Laveen Update] --> | ||
+ | |||
+ | =Minutes= | ||
+ | Attendees: Bill, Igal, Liping, Sasha, Zhikun, Laveen, Phil, Jane, Vlad, Axel, Olga, S.T. | ||
+ | * No change in delivery date for HV boxes | ||
+ | ** Mounting location to be determined | ||
+ | ** Installation in December? | ||
+ | * Still working on increasing light output for LMS | ||
+ | ** Increase number of LEDs to 25 in existing design | ||
+ | * Working on improving fan implementation to reduce heat in ECAL divider region | ||
+ | ** Some regions where air flow is low increase to >125F when the dividers are at HV | ||
+ | ** Heat can transfer from PMT divider region to crystals | ||
+ | ** Decreasing chiller temperature did not obviously change the temperature profile | ||
+ | ** Receiving new/bigger fans will take about 2-3 weeks | ||
+ | * Some fibers delivering small amount of light, added additional fibers to faces of some crystals | ||
+ | ** After fixing a few, decided to move forward with sealing the front face of the FCAL | ||
+ | * Laveen presented COMCAL drawings for reference PMT apparatus, to be modified for ECAL | ||
+ | ** Need to add soft iron housing | ||
+ | ** Also working on restoring TAC (had used Crytur crystals, now using SICCAS crystals) | ||
+ | * Zhikun showed results of looking at data from cosmic runs | ||
+ | ** Holes seen that were fixed over the course of multiple runs over several days | ||
+ | ** Fit pulse integral distributions with Landau+polynomial background | ||
+ | ** Also looked at peak positions using amplitudes | ||
+ | ** Found mean values, see variations from channel to channel due to fixed 1040 V high voltage setting for all channels | ||
+ | ** Plan to adjust HV settings and check with more cosmic runs |
Latest revision as of 08:21, 19 November 2024
Connection
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL -- Sasha
Installation of the FCAL2 detector & integration to GlueX -- Sasha, All
- Implementing ECAL into the GlueX DAQ [3]
- - rocecal3 crate was fixed [4] (initial DAQ implementation [5])
- - implementing flash ADC scalers [6][7]
- - translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [8]
- - implementing and verifying ECAL LMS trigger [9]
- - implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [10]
- - Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- - The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now
- - New version of DAQ, VTP included as a DAQ component [11]
- Installation of scintillating paddles for cosmic tests [12] [13][14]
- ECAL HV interlock check [15]
- Cable map of the ECAL LG modules after installing ECAL [16]
- Reinstalling cables on the ECAL LV distribution board [17]
- Safety briefings - Vlad, Sasha
- Detector installation page
- Commissioning north part of the ECAL (instrumented with 2 temporary HV distribution boards) [18][19][20][21]
- First cosmic event in the ECAL [22]
- Temperature scan in the ECAL divider region [23][24][25][26]
- Meeting with Tim, additional fans will be installed
- Repairing a few ECAL LMS optical fibers [27][28]
- Preparing for the installation of the insulation on the detector face
- FCAL2 Engineering Meetings
- Remaining installation tasks
- - Installing additional fans
- - Installing insulation on the detector's face
Restoring PS test setup [31]
ECAL commissioning -- Sasha, All
Laveen update[[32]]
Calibrations
Analysis/Simulation
Minutes
Attendees: Bill, Igal, Liping, Sasha, Zhikun, Laveen, Phil, Jane, Vlad, Axel, Olga, S.T.
- No change in delivery date for HV boxes
- Mounting location to be determined
- Installation in December?
- Still working on increasing light output for LMS
- Increase number of LEDs to 25 in existing design
- Working on improving fan implementation to reduce heat in ECAL divider region
- Some regions where air flow is low increase to >125F when the dividers are at HV
- Heat can transfer from PMT divider region to crystals
- Decreasing chiller temperature did not obviously change the temperature profile
- Receiving new/bigger fans will take about 2-3 weeks
- Some fibers delivering small amount of light, added additional fibers to faces of some crystals
- After fixing a few, decided to move forward with sealing the front face of the FCAL
- Laveen presented COMCAL drawings for reference PMT apparatus, to be modified for ECAL
- Need to add soft iron housing
- Also working on restoring TAC (had used Crytur crystals, now using SICCAS crystals)
- Zhikun showed results of looking at data from cosmic runs
- Holes seen that were fixed over the course of multiple runs over several days
- Fit pulse integral distributions with Landau+polynomial background
- Also looked at peak positions using amplitudes
- Found mean values, see variations from channel to channel due to fixed 1040 V high voltage setting for all channels
- Plan to adjust HV settings and check with more cosmic runs