* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/October_19,_2022_FCAL_Insert_Installation_Meeting | * Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/October_19,_2022_FCAL_Insert_Installation_Meeting | ||
* Discuss Lead Glass and crystal module removal/install [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha | * Discuss Lead Glass and crystal module removal/install [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha | ||
+ | * Manpower and task division [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha | ||
* Initial testing of modules before removal - Mark D. | * Initial testing of modules before removal - Mark D. | ||
* Revisited removal of darkroom - | * Revisited removal of darkroom - |
Revision as of 09:50, 2 November 2022
Meeting Time and Place
Wednesday November 02, 2022 10am At Jefferson Lab, Hall D Counting House and on Teams
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/October_19,_2022_FCAL_Insert_Installation_Meeting
- Discuss Lead Glass and crystal module removal/install [1] - Sasha
- Manpower and task division [2] - Sasha
- Initial testing of modules before removal - Mark D.
- Revisited removal of darkroom -
- All cables need to be removed from darkroom to be able to install new detector
- Maybe able to crane frame off platform partially assemble
- Rework for patch panels
- Cable discussion fruitful
- Option D to move cables from inner 400 cables to adjacent crate
- Remove 2 crates and move to new racks
- Abandon 200 cables
- Patch panels worked out, 2 HV and 2 LV north and south side, 1 signal feedthrough plate downstream wall
- HV and LV cable length = 20 ft
- Signal cable length = 16 ft
- Cable trays for Signal all going N-S under platform
- HV and LV cables al come from underneath also
- Monitoring system discussion
- Assembly in ESB
- Media:FCAL2_strawman_schedule.pdf