Difference between revisions of "Jan 22, 2009 BCAL Construction"
From GlueXWiki
(→Documents to Review) |
(→Documents to Review) |
||
Line 17: | Line 17: | ||
# Dan's drawing of a leveling system for BCAL modules (will be posted before the meeting) | # Dan's drawing of a leveling system for BCAL modules (will be posted before the meeting) | ||
− | # Electropneumatic Press [http://argus.phys.uregina.ca/cgi-bin/ | + | # Electropneumatic Press [http://argus.phys.uregina.ca/cgi-bin/public/DocDB/ShowDocument?docid=1187 photos] |
− | # Electropneumatic Press [http://argus.phys.uregina.ca/cgi-bin/ | + | # Electropneumatic Press [http://argus.phys.uregina.ca/cgi-bin/public/DocDB/ShowDocument?docid=1188 videos] |
# Updated Wedge drawing: [http://www.jlab.org/~whitey/BCAL/WEDGE_MACH_12-10-08.pdf Latest wedge machined dwg] | # Updated Wedge drawing: [http://www.jlab.org/~whitey/BCAL/WEDGE_MACH_12-10-08.pdf Latest wedge machined dwg] | ||
# Updated Base plate drawing: [http://www.jlab.org/~whitey/BCAL/BASE_PLT_12-10-08.pdf Latest base plate dwg] need to remove inserts for machining | # Updated Base plate drawing: [http://www.jlab.org/~whitey/BCAL/BASE_PLT_12-10-08.pdf Latest base plate dwg] need to remove inserts for machining |
Revision as of 16:55, 19 January 2009
Contents
Teleconference Instructions
Meeting time 14:00-15:00 Newport News / 13:00-14:00 Regina / 12:00-13:00 Edmonton
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 39527048# (remember the "#")
Quick Reference Links
Documents to Review
- Dan's drawing of a leveling system for BCAL modules (will be posted before the meeting)
- Electropneumatic Press photos
- Electropneumatic Press videos
- Updated Wedge drawing: Latest wedge machined dwg
- Updated Base plate drawing: Latest base plate dwg need to remove inserts for machining
Tentative Agenda
- Announcements
- Swager reactivation
- Beam/plate leveling on machining and layup tables
- Installation: how to lift matrix from Al base plate off steel beam
- Latest changes to drawings
- Review action item list
- Other business
Action Item List
-
Tim will supply updated drawings and post on DocDB by this friday -
Swager reactivation and rolling spacing check (Zisis/George) - Gilbert will submit a list of all tools required and cost estimates by middle of next week. Mostly completed.
- Gilbert will send a drawing of the machining set up for Jlab to reference.
- Detailed schedule for preparation for module production (Gilbert).
-
Tim to supply 3d stp/iges files to Regina/Alberta. - In progress: George submitted a QA plan last month. Needs to be reviewed by Tim and Elke.
- Manpower
- Construction Manager: Progress at UofA on job description, job ad
- Co-Op job ads
Minutes
Attendees: Regina - Zisis, George, Dan, Keith Alberta - Gilbert, Jan, JLAB - Tim, James