Difference between revisions of "Run Planning Meeting Notes, November 11 - November 17, 2021"
From GlueXWiki
(→Friday November 12) |
|||
Line 10: | Line 10: | ||
#* bad f250 in TAGH [https://logbooks.jlab.org/entry/3940210] - no longer an issue (Sasha power-cycled the crate) | #* bad f250 in TAGH [https://logbooks.jlab.org/entry/3940210] - no longer an issue (Sasha power-cycled the crate) | ||
#* transmission - Hovanes will do AC scan when the beam is back after 10am - profiler doesn't lock has to be fixed at that time, as well | #* transmission - Hovanes will do AC scan when the beam is back after 10am - profiler doesn't lock has to be fixed at that time, as well | ||
− | # [https://halldweb.jlab.org/ | + | # [https://halldweb.jlab.org/wiki/index.php/SRC/CT_Run_Plan Plan:] |
#* Down starting at 10am: for 1+ hours (Hall A changes to 4 passes) - FCAL items will be surveyed | #* Down starting at 10am: for 1+ hours (Hall A changes to 4 passes) - FCAL items will be surveyed | ||
#* Continue production at 150nA on diamond | #* Continue production at 150nA on diamond |
Revision as of 23:25, 12 November 2021
Friday November 12
- Last 24h:
- Issues:
- bad f250 in TAGH [6] - no longer an issue (Sasha power-cycled the crate)
- transmission - Hovanes will do AC scan when the beam is back after 10am - profiler doesn't lock has to be fixed at that time, as well
- Plan:
- Down starting at 10am: for 1+ hours (Hall A changes to 4 passes) - FCAL items will be surveyed
- Continue production at 150nA on diamond
- Analysis update