RC summary, 09/29/2021 - 10/06/2021, Keigo Mizutani | RC summary, 09/29/2021 - 10/06/2021, Keigo Mizutani | ||
− | This week, we | + | This week, we restarted PrimEx production on Be target with a 50 nA beam at 2:40 am on Friday, 1 October 2021. We had no beam on Wednesday and Thursday (29, 30 September) due to machine maintenance and subsequent accelerator troubles. After beam came back, we spent 3 hours for the debugging of trigger issue (a problematic FCAL FADC was replaced). |
Revision as of 20:43, 25 October 2021
RC summary, 09/29/2021 - 10/06/2021, Keigo Mizutani
This week, we restarted PrimEx production on Be target with a 50 nA beam at 2:40 am on Friday, 1 October 2021. We had no beam on Wednesday and Thursday (29, 30 September) due to machine maintenance and subsequent accelerator troubles. After beam came back, we spent 3 hours for the debugging of trigger issue (a problematic FCAL FADC was replaced).