Difference between revisions of "Run Planning Meeting Notes, September 9 - September 15, 2021"
From GlueXWiki
(Created page with "<- Back to Run Coordination Meetings:Summer2021 =Tuesday, September 14= # Last 24 hours: #* [https://logbooks.jlab.org/entry/3904977 PD Update] # Report/issue #* [https:...") |
(→Tuesday, September 14) |
||
Line 9: | Line 9: | ||
## rocfcal11 cannot be remotely rebooted | ## rocfcal11 cannot be remotely rebooted | ||
## Sometimes whole crates are missing from CSS view. | ## Sometimes whole crates are missing from CSS view. | ||
− | ## Sometimes single | + | ## Sometimes single 16 ch fADCs report 0. |
− | ## Sometimes CSS on | + | ## Sometimes CSS on gluon02 doesn't show the same thing as CSS on gluon03. |
# Run plan | # Run plan | ||
#* Wait for beam delivery. Begin experiment commissioning. [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Run plan] | #* Wait for beam delivery. Begin experiment commissioning. [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Run plan] |
Revision as of 08:40, 14 September 2021
<- Back to Run Coordination Meetings:Summer2021
Tuesday, September 14
- Last 24 hours:
- Report/issue
- 4 FCAL bases replaced
- Problems with FCAL scalers. example
- rocfcal11 cannot be remotely rebooted
- Sometimes whole crates are missing from CSS view.
- Sometimes single 16 ch fADCs report 0.
- Sometimes CSS on gluon02 doesn't show the same thing as CSS on gluon03.
- Run plan
- Wait for beam delivery. Begin experiment commissioning. Run plan