Difference between revisions of "January 6, 2020 DIRC"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 19: | Line 19: | ||
#* [https://mailman.jlab.org/pipermail/halld-pid-upgrade/2019-December/000473.html Instr2020 abstract submitted] (Bill) | #* [https://mailman.jlab.org/pipermail/halld-pid-upgrade/2019-December/000473.html Instr2020 abstract submitted] (Bill) | ||
# Spring 2020 preparation | # Spring 2020 preparation | ||
− | #* North OB inspection | + | #* [https://logbooks.jlab.org/entry/3758003 North OB inspection complete] |
#* High speed network card (ongoing) | #* High speed network card (ongoing) | ||
#* HV board swap | #* HV board swap | ||
Line 34: | Line 34: | ||
#** Samples for both Spring 2019 (commissioning) and Fall 2019 (borosilicate mirrors) will be produced | #** Samples for both Spring 2019 (commissioning) and Fall 2019 (borosilicate mirrors) will be produced | ||
--> | --> | ||
− | #* Commissioning | + | #* Commissioning analyses (All) |
− | #* | + | #* [https://logbooks.jlab.org/entry/3757897 Bar-by-bar diagnostics] |
− | #* | + | #* Standalone LUT update (Ahmed/Roman) |
− | #* | + | #* FastDIRC update (Yunjie) |
+ | #* Update on kaon track timing issue (Justin) | ||
# Meetings: | # Meetings: | ||
#* Is the current meeting time OK for this semester? | #* Is the current meeting time OK for this semester? |
Revision as of 12:20, 3 January 2020
Meeting Information
GlueX DIRC Meeting
Monday January 6, 2029
1:00 pm, EDT
CC F326
Connection Using Bluejeans
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
- To join via phone, use one of the following numbers and the Conference ID: 846453895
- US or Canada: +1 408 740 7256 or
- US or Canada: +1 888 240 2560
- More information on connecting to bluejeans is available.
Agenda
- Announcements:
- Instr2020 abstract submitted (Bill)
- Spring 2020 preparation
- North OB inspection complete
- High speed network card (ongoing)
- HV board swap
- Water level sensors
- 2019 commissioning review
- Spring 2019 DIRC Commissioning Analysis (All)
- Fall 2019 Commissioning Analysis (All)
- Latest data files:
- dirc_tree files: /volatile/halld/home/gxproj7/RunPeriod-2019-11/dirc_monitoring/ver01/hists/merged/
- DIRC LED skims: /volatile/halld/home/gxproj7/RunPeriod-2019-11/dirc_monitoring/ver01/DIRC-LED/
- REST files: /volatile/halld/home/gxproj7/RunPeriod-2019-11/dirc_monitoring/ver01/REST/
- Commissioning analyses (All)
- Bar-by-bar diagnostics
- Standalone LUT update (Ahmed/Roman)
- FastDIRC update (Yunjie)
- Update on kaon track timing issue (Justin)
- Meetings:
- Is the current meeting time OK for this semester?
- Could we schedule a DIRC "workfest" (i.e. DIRCfest) for later this Spring?
- Goal 1: provide DIRC reconstruction algorithm and calibrations for data production campaign in Summer 2020.
- Goal 2: performance plots and conclusions for PAC jeopardy and DIRC NIM article
- Requires significant work beforehand. Possibly schedule around Collaboration Meeting after the run: May 4-6
- AOB