Difference between revisions of "Run Planning Meeting Notes, Feb 28 - Mar 6, 2019"
From GlueXWiki
(→Thursday, Feb. 28 at 08:45) |
(→Thursday, Feb. 28 at 08:45) |
||
Line 10: | Line 10: | ||
#* Compton Production: ??? M triggers with Be | #* Compton Production: ??? M triggers with Be | ||
# Issues: | # Issues: | ||
+ | #* FYI: [https://logbooks.jlab.org/entry/3660650 Beam orbit locks off] | ||
# Today: | # Today: | ||
#* Remove Be target @ 8 AM, lockup Hall by noon? | #* Remove Be target @ 8 AM, lockup Hall by noon? |
Revision as of 16:45, 27 February 2019
Contents
- Run_Coordination_Meetings:Spring2019_Run
- PrimEx-η run plan
- To join via a Web Browser, go to the page https://bluejeans.com/660743227
Thursday, Feb. 28 at 08:45
- Past 24 hours:
- Compton Production: ??? M triggers with Be
- Issues:
- FYI: Beam orbit locks off
- Today:
- Remove Be target @ 8 AM, lockup Hall by noon?
- Empty target production until Friday morning?
- Tomorrow:
- LHe target install:
- Schedule?
- Other work in the Hall?
- LHe target install: