Line 29: | Line 29: | ||
#* [[Media:DIRC_INSTALL_SCHEDULEv2.pdf|Current "optimistic" schedule]]: optical box delivery July 14 | #* [[Media:DIRC_INSTALL_SCHEDULEv2.pdf|Current "optimistic" schedule]]: optical box delivery July 14 | ||
#* Contingency: [[Media:Oct OB delivery.pdf|Latest possible installation schedule]]: optical box delivery October 10 | #* Contingency: [[Media:Oct OB delivery.pdf|Latest possible installation schedule]]: optical box delivery October 10 | ||
− | #* Requirements for mechanical install of optical box: [[Media:Aug10_OB_delivery.pdf|Aug 10 installation schedule]] | + | #* Requirements for mechanical install of optical box: [[Media:Aug10_OB_delivery.pdf|Aug 10 installation schedule]] |
+ | #** Delivery of outer optical box (mirror box not required), window, flange, and gasket by August 10 | ||
+ | #** Goals (reduce risk for final installation): | ||
+ | #*** Test water tightness of optical box and interface with bar boxes | ||
+ | #*** Flow water through full system and establish controls, N2 purge, etc. | ||
# Mirror box laser alignment | # Mirror box laser alignment | ||
#* [https://halldweb.jlab.org/DocDB/0035/003581/002/2018_July_19.pdf Update on geometry and laser projections] (Bill) | #* [https://halldweb.jlab.org/DocDB/0035/003581/002/2018_July_19.pdf Update on geometry and laser projections] (Bill) |
Revision as of 09:52, 19 July 2018
Meeting Information
GlueX DIRC Optical Box Meeting
Thursday July 19, 2018
10:00 am, EST
JLab A110
Connection Using Bluejeans
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
- To join via phone, use one of the following numbers and the Conference ID: 846453895
- US or Canada: +1 408 740 7256 or
- US or Canada: +1 888 240 2560
- More information on connecting to bluejeans is available.
Agenda
- Announcement
- Optical box status
- Fabrication status update (Ernie and Jason)
- Box production at Lesker
- Mirror strong back delivery and assembly
- Mirror cutting
- Window procurement
- Assembly sequence and testing plans at Bates
- Dark box enclosure development: air flow calculations
- DIRC BBox Split Flange Seal (Jim/Tim)
- Fabrication status update (Ernie and Jason)
- Installation schedule discussion:
- Current "optimistic" schedule: optical box delivery July 14
- Contingency: Latest possible installation schedule: optical box delivery October 10
- Requirements for mechanical install of optical box: Aug 10 installation schedule
- Delivery of outer optical box (mirror box not required), window, flange, and gasket by August 10
- Goals (reduce risk for final installation):
- Test water tightness of optical box and interface with bar boxes
- Flow water through full system and establish controls, N2 purge, etc.
- Mirror box laser alignment
- AOB