Difference between revisions of "April 19, 2018 DIRC"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 17: | Line 17: | ||
# Announcements | # Announcements | ||
− | #* Fall 2018 run start is officially August 21 | + | #* Fall 2018 run start is officially August 21. |
+ | #* Expect to complete "low intensity GlueX" by October ~1. | ||
# Support structure update (John, Tim, Mark) | # Support structure update (John, Tim, Mark) | ||
#* Roll fixture testing | #* Roll fixture testing |
Revision as of 07:36, 19 April 2018
Meeting Information
GlueX DIRC Meeting
Thursday April 19, 2018
10:00 am, EDT
JLab room A110
Connection Using Bluejeans
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
- To join via phone, use one of the following numbers and the Conference ID: 846453895
- US or Canada: +1 408 740 7256 or
- US or Canada: +1 888 240 2560
- More information on connecting to bluejeans is available.
Agenda
- Announcements
- Fall 2018 run start is officially August 21.
- Expect to complete "low intensity GlueX" by October ~1.
- Support structure update (John, Tim, Mark)
- Roll fixture testing
- Bar box transportation
- Crate fabrication (John)
- Monitoring system procurements
- At JLab: 2 additional switches and 6 additional cameras (assembly with plates in progress)
- LORD accelerometers and base station with Yunjie for testing
- LED strips?
- Meeting with SLAC last week
- Followup on paperwork: radiation control release, property transfer, and work order agreement
- Optical box
- Status update (Ernie and Jason)
- Box production at Lesker
- PMT test fixture
- Window procurement
- Status update (Ernie and Jason)
- Simulation studies (Maria and Roman)
- MAPMT testing (Bill)
- AOB