Difference between revisions of "BLTWG Meeting 04/15/2013"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 12: | Line 12: | ||
# Report on the fixed array construction - ''Franz'' | # Report on the fixed array construction - ''Franz'' | ||
#* [http://faculty.cua.edu/sober/HallD/Counter_table_and_plots_22April13.html latest fixed array layout] | #* [http://faculty.cua.edu/sober/HallD/Counter_table_and_plots_22April13.html latest fixed array layout] | ||
− | # [http:// | + | # Report on the microscope construction - ''James'' |
+ | #* [http://zeus.phys.uconn.edu/halld/glueXmeetings/mtg-4-15-2013/TAGM-Construction-Update-15Apr2013.docx Updated progress and schedule] | ||
+ | #* [http://zeus.phys.uconn.edu/halld/glueXmeetings/mtg-4-15-2013/Ferrule-Size.pptx Progress on fiber fusing] | ||
# Status of the microscope electronics construction - ''Alex'' | # Status of the microscope electronics construction - ''Alex'' | ||
# Update on polarimetry - ''Mike'' | # Update on polarimetry - ''Mike'' |
Revision as of 11:27, 15 April 2013
Organization
- Time: 11:30 EST
- Place: ESNET and Seevogh (Jlab community)
- Connecting: instructions are here
- Present:
Agenda
- Announcements
- Report on construction of the PS detectors - Sascha
- Report from accelerator liaison - Todd
- Report on the fixed array construction - Franz
- Report on the microscope construction - James
- Status of the microscope electronics construction - Alex
- Update on polarimetry - Mike
- Discussion of installation issues - James
- Draft of tagger magnet mapping plan - Dan
- any other business