Difference between revisions of "Dec 5, 2011 SiPM Electrical and Cooling"
From GlueXWiki
m (moved Nov 15, 2011 SiPM Electrical and Cooling to Dec 5, 2011 SiPM Electrical and Cooling: change date) |
|||
Line 1: | Line 1: | ||
== Action Items from previous meetings == | == Action Items from previous meetings == | ||
− | # Decide on cable connections for monitoring cable from Bcal wedge to patch panel. Consider electronics needed for pulsing system (Elton and Fernando) | + | # <strike> Decide on cable connections for monitoring cable from Bcal wedge to patch panel. Consider electronics needed for pulsing system (Elton and Fernando) </strke,> Decided to have a separate patch panel, which allows decisions on these other items to a later date |
− | # Make a metal die to punch holes in cooling mat to ease assembly. (Nick and Jim) | + | # <strike> Make a metal die to punch holes in cooling mat to ease assembly. (Nick and Jim) </strke> |
− | # Give Jim a U-board with defective SiPM for devising extraction tool (Nick and Yi) | + | # <strike> Give Jim a U-board with defective SiPM for devising extraction tool (Nick and Yi) </strike> |
− | # Determine granularity of LED bias and power, as well as multiplicity of trigger signals (Elton) | + | # <strike> Determine granularity of LED bias and power, as well as multiplicity of trigger signals (Elton) </strike> |
# Check on official releases of the 3D model (Elton and Jim) | # Check on official releases of the 3D model (Elton and Jim) | ||
Revision as of 17:16, 5 December 2012
Action Items from previous meetings
-
Decide on cable connections for monitoring cable from Bcal wedge to patch panel. Consider electronics needed for pulsing system (Elton and Fernando) </strke,> Decided to have a separate patch panel, which allows decisions on these other items to a later date - <strike> Make a metal die to punch holes in cooling mat to ease assembly. (Nick and Jim) </strke>
- <strike> Give Jim a U-board with defective SiPM for devising extraction tool (Nick and Yi)
-
Determine granularity of LED bias and power, as well as multiplicity of trigger signals (Elton) - Check on official releases of the 3D model (Elton and Jim)
Tentative Agenda
- Announcements
- Action Items
- Schedule for production and testing (all)
- mini-Bcal (Elton)
- SiPM production testing (Yi)
- Mechanical assembly (Jim)
- Temperature compensation (Jack)
- Electronic boards (Fernando and Chris)
- Light guide gluing setup (Scot)
Minutes