Difference between revisions of "Mini FCAL Meeting Mon. Mar. 05, 2012"
From GlueXWiki
(Created page with "Minutes FCAL add additional remote scintillator before final Hall B run Kei's working Geant simulations, see http://dustbunny.physics.indiana.edu/~kmoriya/FCALGEANT/ BCAL ...") |
|||
Line 5: | Line 5: | ||
add additional remote scintillator before final Hall B run | add additional remote scintillator before final Hall B run | ||
− | Kei's working Geant simulations, see | + | Kei's working Geant simulations, see links below. Color coding for particles are |
+ | * <span style="color:#FF0000">red</span> - negative charge (e-) | ||
+ | * <span style="color:#0000FF">blue</span> - positive charge (e+) | ||
+ | * <span style="color:#0000FF">green</span> - neutrals (gamma rays) | ||
+ | Note that the code does not track optical photons, only energetic gamma rays. | ||
+ | *[https://halldweb1.jlab.org/wiki/images/a/ab/0.2 GeV_overview.pdf Simulation overview at 0.2GeV] | ||
+ | *[https://halldweb1.jlab.org/wiki/images/9/9a/0.2 GeV_detector.pdf Detector response at 0.2GeV] | ||
+ | *[https://halldweb1.jlab.org/wiki/images/a/ab/1 GeV_overview.pdf Simulation overview at 1 GeV] | ||
+ | *[https://halldweb1.jlab.org/wiki/images/9/9a/1 GeV_beam.pdf Detector response at 1 GeV] | ||
+ | *[https://halldweb1.jlab.org/wiki/images/9/9a/1 GeV_detector.pdf Detector response at 1 GeV] | ||
BCAL | BCAL |
Revision as of 15:50, 5 March 2012
Minutes
FCAL
add additional remote scintillator before final Hall B run
Kei's working Geant simulations, see links below. Color coding for particles are
- red - negative charge (e-)
- blue - positive charge (e+)
- green - neutrals (gamma rays)
Note that the code does not track optical photons, only energetic gamma rays.
- GeV_overview.pdf Simulation overview at 1 GeV
- GeV_beam.pdf Detector response at 1 GeV
- GeV_detector.pdf Detector response at 1 GeV
BCAL
waiting on 1 light guide and the monitoring system to arrive
few simple metal parts to be fabricated
hope to finish detector this week and connect to stand by next week
installation estimate of March 21
scalars will be archived in EPICS
- NEW MEETING TIME ***** MONDAYS AT 1:30 **************