June 30, 2011 FDC meeting
Agenda
- Production (Dave)
- Status Construction Tracking
- Second cell HV tests
- Radioactive source usage at Blue Crab
- Other
- Engineering (Bill)
- Package flatness measurements
- FDC cabling
- Other: gusset rings, lifting frame
- Electronics update (Fernando, Chris)
- Chamber testing at EEL126 (Beni, Lubomir)
- First cell status top/bottom asymmetry
- Future plans
- Other