Difference between revisions of "Minutes-9-23-2010"
Line 29: | Line 29: | ||
== Electronics == | == Electronics == | ||
+ | - Fernando: we have now all the PCB boards (except maybe one set, out of 28, that has to be checked). The contract with the assembly company is awarded. | ||
+ | |||
+ | - Fernando: according to the procurement, the sole source for the cathode foils is out of question. Therefore, Fernando submitted the specifications | ||
+ | to be posted on the FedBiz site with a deadline for possible offers of Oct. 13. | ||
+ | |||
+ | - Lubomir started preparing a document | ||
<!-- | <!-- | ||
Revision as of 18:48, 23 September 2010
September 23, 2010 FDC meeting
Tentative Agenda
- Production
- Clean room update
- Electronics
- update (Fernando)
- discussions of the FDC requirements for the pre-amplifiers and fADC125 [FDC requirements],[FDC Log Book, pages 516-517]
- Engineering
- Full-scale prototype
- test update (Beni)
- momentum resolution studies [FDC Log Book, pages 515] (Simon)
- Other
Minutes
Participants: Eugene, Fernando, Beni, Bill, Chris, David, Simon, Gerard (on the phone), and Lubomir.
It was a long (2.5 hours) but productive meeting, half of the time discussing the FDC requirements for the electronins, and the other half - the wire stringing procedure.
Production
- Only good news about Blue Crab, procurement will finalize the contract with AdvanceTEC for the construction of the clean room by the end of the month. The AC for the whole area is being installed now.
Electronics
- Fernando: we have now all the PCB boards (except maybe one set, out of 28, that has to be checked). The contract with the assembly company is awarded.
- Fernando: according to the procurement, the sole source for the cathode foils is out of question. Therefore, Fernando submitted the specifications to be posted on the FedBiz site with a deadline for possible offers of Oct. 13.
- Lubomir started preparing a document