= Minutes = | = Minutes = | ||
− | Participants: | + | Participants: Fernando, Casey, Roger, Brian, Glenn, Bill, Kim, Simon, Beni, Eugene, Lubomir |
− | == Production == | + | == Production space == |
− | - | + | - Tim is the contact person from our side for the 727 B.C. property. He will meet with Rusty to discuss our requirements and all the details. There was a meeting with the network people from the computer center. They will organize the network using their equipment. We will pay for the COX business connection. |
− | - | + | - A document has been created (attached above) with the intention to list all the steps of the FDC production and describe them in terms of manpower and time. Lubomir will seek help from Brian and Mark to estimate the manpower required for each step. The wire stringing procedure will be based on the UVA experience. Then Bill will review the document and we will continue with creating a flowchart of the production. |
− | + | ||
− | + | ||
− | == | + | == Electronics == |
− | - | + | - PCBs: some minor modifications have been done and the design is now final. Kim got quotes from |
- Cathode redesign: Roger had several questions related to the ground of the cathode daughter board (flex) design, and also the strip labels. | - Cathode redesign: Roger had several questions related to the ground of the cathode daughter board (flex) design, and also the strip labels. | ||
+ | |||
+ | <!-- | ||
- Bill explained the proposed design of the cable bundles and the installation procedure. Still, we have to decide about the total number of cables and get accurate info about their sizes. This includes 528 (+ 24/48spare?) signal cables, 264 thin low voltage cables, 8 HV cables, 4 grounding cables, 48 gas pipes, 8? cooling lines. We are considering also to do some prototype cable bundles to make sure it works. Expect more discussion on the next meeting. | - Bill explained the proposed design of the cable bundles and the installation procedure. Still, we have to decide about the total number of cables and get accurate info about their sizes. This includes 528 (+ 24/48spare?) signal cables, 264 thin low voltage cables, 8 HV cables, 4 grounding cables, 48 gas pipes, 8? cooling lines. We are considering also to do some prototype cable bundles to make sure it works. Expect more discussion on the next meeting. |
Revision as of 15:31, 29 April 2010
April 29, 2010 FDC meeting
Tentative Agenda
- Production space
- status
- off-site space production planning
- Electronics
- PCB (Kim, Fernando)
- grounding/oscillation tests (Lubomir)
- Cathode redesign (Roger) beam hole, fdc left, cathode adapter
- Cosmic tests (Beni)
- results from the first tests FDC Log Book
- plans
- Other
- talks at the Collaboration meeting
- open house