May 28, 2010
- Arrange a meeting to discuss signal splitting schemes for the TOF PMT signals.
- Think about light collection studies for the TOF.
March 19, 2010
- FSU MOU -> Paul
- UMass MOU -> Rory
- Target refrigerator order -> Chris K.
- FSU Hamamastu PMT order -> Paul
- Project schedule review -> Mark
October 2, 2009
-
Put new start counter geometry into HDDS-> Sascha, Mark -
Broaden discussion of adding target design/construction to TOF/SC meeting-> Mark
August 7, 2009
-
Reconcile target area geometry version: Mark
June 12, 2009
-
Tim will find a copy of Chuck's drawing of the target area to show us. - Elliott will ship a flash ADC to FSU for their test set-up.
-
FIU will study different geometries for the start counter. - Sasha will look at the bugs in his single-pi HDGeant study which uses the time-of-flight.