Difference between revisions of "Oct 15, 2009 Calorimetry"

From GlueXWiki
Jump to: navigation, search
(Tentative Agenda)
(Tentative Agenda)
Line 34: Line 34:
 
#* SiPM testing  (Carl and Fernando)
 
#* SiPM testing  (Carl and Fernando)
 
#* New geometry for light guides (Alam/Pedro)
 
#* New geometry for light guides (Alam/Pedro)
#* Light guide prototypes. See [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1365# Quote from Plastic Craft]
+
#* Light guide prototypes. See [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1365# Quote from Plastic Craft] and [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1367 Ray tracing through light guides]
 
# Other business
 
# Other business
  

Revision as of 09:52, 15 October 2009

Teleconference Time: 11:00 a.m. EST

  • ESNET and EVO session
  • Phone only if requested:
    • +1-800-377-8846 : US
    • +1-888-276-7715 : Canada
    • +1-302-709-8424 : International
    • then enter participant code: 77438230# (remember the "#"). Phone line by request only.

Items for followup from previous meeting(s)

  1. Fcal
    • Need to discuss strategy for fabrication of boards. Paul is concerned primarily about the HV board. We should include Fernando and Chris on the discussion for suggestion of production.
    • CR to modify schedules for new activities, including Fcal calibration. Elton to send proposal to listserver for comments.
  2. Bcal
    • Web page needs to be setup for communications.
    • Decide on a strategy for how to use fibers with slightly different systematics into matrix construction (e.g. randomizing them in the matrix). (everyone)
  3. Bcal readout
    • Review decision on the orientation of FM pmt relative to Bfield, including tolerances due to expected field changes. (Elton, Will, Alam, Pedro)
    • Alam will see if Pedro can generate new orientations of the pmts at an angle of 15 deg relative to the B field.
    • Should order prototype light guides for typical configurations

Documents to Review

Tentative Agenda

  1. Announcements
  2. Review of Action Items
  3. Calibration/Monitoring
  4. Fcal
  5. Bcal
    • Status of construction / Readiness Review Schedule
    • Fibre QA: Shipments 1-5 (GlueX-doc-1366)
  6. BCAL Readout
  7. Other business

Minutes

Attendees: