Difference between revisions of "Run Planning Meeting Notes, January 26 - February 1, 2023"
From GlueXWiki
(Created page with "= Thursday January 26 = === Past 24 hours === * Production on diamond. ABU= xx h for the day. === Shift Reports === * [https://logbooks.jlab.org/entry/4117081 Day shift summa...") |
m (→Reports) |
||
Line 10: | Line 10: | ||
=== Reports === | === Reports === | ||
− | * [https://logbooks.jlab.org/entry/ | + | * [https://logbooks.jlab.org/entry/4117252 Alternative to barometric pressure measurement (Naomi)]. Whiteboard instructions have been updated. |
+ | * [https://logbooks.jlab.org/entry/4117303 Online calibrations started (Sean)] | ||
* MCC is scheduling maintenance for Feb 1st | * MCC is scheduling maintenance for Feb 1st | ||
Revision as of 23:21, 25 January 2023
Thursday January 26
Past 24 hours
- Production on diamond. ABU= xx h for the day.
Shift Reports
Reports
- Alternative to barometric pressure measurement (Naomi). Whiteboard instructions have been updated.
- Online calibrations started (Sean)
- MCC is scheduling maintenance for Feb 1st
Issues
- Follow up on HallD dp variation
- Start counter 96 degree rotation in cabling or software space (Simon).
- Tentative plan of action: To turn off the low voltage to the SiPM bias for a few specific start counter paddles and take a 1-hour run where we can identify the physical location of these paddles using the tracking detectors.
- DIRC LED TDC missing (David Lawrence, Justin DIRC SiPM reference signal (Justin)
- Tentative plan of action: Since no spare inverter box is available, Chris Stanislav will investigate if a simple box can be built.
Pending:
- BCM calibration. Accelerator instrumentation group informed us that last BLA calibration was done in 2021 (beside that done last Thursday, 01/19/2023? To be confirmed) and recommend Ops to do one at each start of the run period.
- A request for the kitchen lights to be fixed should be submitted next time there is beam downtime.
Plans
- Production (300 nA, 2h runs) with cycle:
- 2 runs para(0/90)
- 2 runs perp(0/90)
- 2 runs para(45/135)
- 2 runs perp(45/135)
- 1 run amo (use it to rejuvenate amo reference in CBREM GUI)
- Trigger fine tuning Thursday? (A. Somov)