Difference between revisions of "JEF meeting, November 11, 2022"
From GlueXWiki
Line 17: | Line 17: | ||
*** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf All SICCAS 576 SICCAS] | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf All SICCAS 576 SICCAS] | ||
*** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 759 CRYTUR], available: 20 | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 759 CRYTUR], available: 20 | ||
+ | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/11_11_22 Moving modules to the new lab (EEL108)] | ||
* '''Preparation for the FCAL2 installation (coordination with Tim's group)''' -- Sasha | * '''Preparation for the FCAL2 installation (coordination with Tim's group)''' -- Sasha | ||
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/November_02,_2022_FCAL_Insert_Installation_Meeting November 2022] | ** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/November_02,_2022_FCAL_Insert_Installation_Meeting November 2022] | ||
Line 23: | Line 24: | ||
** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Projects for summer students] | ** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Projects for summer students] | ||
** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Meeting with the detector support group] | ** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Meeting with the detector support group] | ||
− | |||
* '''Light Monitoring System''' -- Arshak | * '''Light Monitoring System''' -- Arshak |
Latest revision as of 10:32, 11 November 2022
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Simulations/Analysis
- Preparation of parts for FCAL2 modules -- Sasha
- Received 25 CRYTUR crystals during this week [1]
- Wrapped CRYTUR crystals: 762
- Available for wrapping: 782 - 762 = 20 (20 crystals were wrapped during last week)
- Mindy (DSG group) continues wrapping crystals
- List of available parts
- Module fabrication -- Sasha
- Status of fabrication
- Fabricated modules: Total 1335 (17 modules fabricated since last week)
- Preparation for the FCAL2 installation (coordination with Tim's group) -- Sasha
- Updates from the meetings with Tim's group November 2022
- Detector cabling and patch panels for the FCAL insert
- Manpower and division of tasks
- Projects for summer students
- Meeting with the detector support group
- Updates from the meetings with Tim's group November 2022
- Light Monitoring System -- Arshak