Difference between revisions of "Run Planning Meeting Notes, August 11- August 17, 2022"
From GlueXWiki
(→Friday August 12) |
|||
Line 28: | Line 28: | ||
= Friday August 12 = | = Friday August 12 = | ||
=== Past 24 hours === | === Past 24 hours === | ||
− | * Beam off 630 am - ?? pm for maintenance day | + | * Beam off Thu 630 am - ?? pm for maintenance day |
− | * ~ 9 am access to tagger hall by Beni to reset TAGH HV crate | + | * ~ 9 am access to tagger hall by Beni to reset TAGH HV crate; OK now |
* ramped down solenoid for cry work (Tim) | * ramped down solenoid for cry work (Tim) | ||
Revision as of 09:30, 11 August 2022
Contents
Thursday August 11
Past 24 hours
- Running on Pb target (30 nA). Another relatively good day: ABU=18.3 h for the day
- Beam down for 3.75 hrs due to afternoon thunderstorms
- Program Deputy summary
Shift Reports
- Day shift summaries (1), (2)
- Swing shift summary (1), (2)
- Owl shift summary
- Early Riser shift summary
Reports
Issues
- Continued: TAGH major link alarm. Description by shift leader. Cannot communicate with crate, but rates are fine -> we decided to run as it is (monitoring TAGH scalars with stripcharts) and have a look latter.
Plans
- Beam off all day for maintenance day
- Hall in controlled access
- Solenoid current to be lowered because of cryowork. Tim seems to be doing this from home as we speak.
- Requested survey of tagger hall for access to reset TAGH crate
- When beam restored run harp scans
- Production on Pb target.
- Next pass change (4->3) for Hall C will be Tuesday. They will be down for 6h-8h Monday to install their aerogel. Monday is auspicious for a TAC run.
Friday August 12
Past 24 hours
- Beam off Thu 630 am - ?? pm for maintenance day
- ~ 9 am access to tagger hall by Beni to reset TAGH HV crate; OK now
- ramped down solenoid for cry work (Tim)