** [https://halldweb.jlab.org/wiki/images/4/4f/Glue-jefxd-igal-jaegle-05082022.pdf New IA vs old IA] -- ig | ** [https://halldweb.jlab.org/wiki/images/4/4f/Glue-jefxd-igal-jaegle-05082022.pdf New IA vs old IA] -- ig | ||
* Preparation of parts for FCAL2 modules -- Sasha | * Preparation of parts for FCAL2 modules -- Sasha | ||
+ | ** Received 25 crystals from CRYTUR (last from our 2nd order). | ||
** Meeting with the DSG group [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/8_5_22/fcal_status_8_2_22.pdf]. Mindy and George will continue working on the project. | ** Meeting with the DSG group [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/8_5_22/fcal_status_8_2_22.pdf]. Mindy and George will continue working on the project. | ||
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf Preparation of parts][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students1.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students2.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students3.jpg] | **[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf Preparation of parts][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students1.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students2.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students3.jpg] |
Revision as of 09:13, 5 August 2022
Meeting time and location=
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Simulations/Analysis
- New IA vs old IA -- ig
- Preparation of parts for FCAL2 modules -- Sasha
- Received 25 crystals from CRYTUR (last from our 2nd order).
- Meeting with the DSG group [1]. Mindy and George will continue working on the project.
- Preparation of parts[2][3][4]
- Preshaping ESR foils (with the DSG)
- Wrapping crystals (with the DSG)
- Preparing Silicon cookies
- Module fabrication
- Cleaning brass assemblies
- Gluing light guides
- Wrapped CRYTUR crystals: 664
- All currently available (consider to borrow some spares from NPS)
- Module fabrication -- Sasha
- Received 85 PMT housings from Tim, they have been honed by Bobby. All of them will be used today.
- Status of fabrication
- Fabricated modules: Total 1121
- All SICCAS 577 SICCAS
- 487 CRYTUR, Remaining: 167
- Clean room EEL126
- Light Monitoring System -- Arshak