Difference between revisions of "Run Planning Meeting Notes, August 3- August 10, 2022"
From GlueXWiki
(→Wednesday August 3) |
(→Wednesday August 3) |
||
Line 17: | Line 17: | ||
* [https://logbooks.jlab.org/entry/4023888 Swing shift summary] | * [https://logbooks.jlab.org/entry/4023888 Swing shift summary] | ||
* [https://logbooks.jlab.org/entry/4024007 Owl shift summary] | * [https://logbooks.jlab.org/entry/4024007 Owl shift summary] | ||
− | * [ Early Riser shift summary] | + | * [https://logbooks.jlab.org/entry/4024097 Early Riser shift summary] |
=== Reports === | === Reports === | ||
* [https://logbooks.jlab.org/entry/4023863 About bleedthrough from Hall C] | * [https://logbooks.jlab.org/entry/4023863 About bleedthrough from Hall C] |
Revision as of 08:01, 4 August 2022
Back to Run Coordination Meetings:Summer2022
Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Wednesday August 3
Past 24 hours
- Running on empty target (60 nA). Everything is going nicely and smoothly.
Shift Reports
Reports
Issues
- temporary main trigger rate increase seems to be due to a hot FCal channel.
- Hot channel in FCAL
- FMWPC Chamber 1 hot wire and trips due to high current
- 2 ns shift
Plans
- Production running on empty target until Thursday
- Thursday morning, TAC run starting ~9am? (7-8 hours, assuming stable beam)
- RF Recovery for 4hrs on Friday to prepare for weekend. Starts at 7:15am.
- Monday day: 5 -> 4 pass change for Hall C (Around 4h. Mostly invasive).