Difference between revisions of "Run Planning Meeting Notes, July 14 - July 20, 2022"
From GlueXWiki
(→Issues) |
(→Features) |
||
Line 29: | Line 29: | ||
=== Features === | === Features === | ||
− | * | + | |
+ | * We would like to add the TOF and CTOF trigger rates to EPICs/archiver | ||
=== Plans === | === Plans === |
Revision as of 10:03, 14 July 2022
Back to Run Coordination Meetings:Summer2022
Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Contents
Thursday July 15
Past 24 hours
- Production on Empty target (~xxxx B events)
- Production on Full Pb target (~xxx B events)
Shift Reports
- [ Day shift summary]
- [ Swing shift summary]
- [ Owl shift summary]
- [ Early Riser shift summary]
Reports
Issues
- Stability of beam position at Active Collimator
Features
- We would like to add the TOF and CTOF trigger rates to EPICs/archiver
Plans
Thursday July 14
Past 24 hours
- Request for a Schedule Adjustment from Jul 27 to Aug 17 has been submitted.
- Production on Full Pb target (~0.5 B events)
- Install Empty Target (12 pm)
- Production on Empty Target (~0.9 B events). Need about twice that. After checking statistics today, I suggest we stay on Empty Target, but run at 60 nA after maintenance.
- Storm Takes Down Accelerator
- Smooth, but trippy, beam after recovery. Trips are at about 15-20 trips/hr
Shift Reports
Reports
Issues
- We would like to add the TOF and CTOF trigger rates to EPICs/archiver
Plans
- RF Recovery today (beam down 8.15 till ~5pm)
- HD Refrigerator Maintenance
- Access for Sasha and Vlad to install modules in PS Test Stand
- Nick to work on DIRC environment
- Following Maintenance: Plan to continue with Empty Target data to complete the data taking cycle and then continue at 60 nA