Difference between revisions of "Run Planning Meeting Notes, November 11 - November 17, 2021"
From GlueXWiki
Line 9: | Line 9: | ||
#Issues: | #Issues: | ||
#* bad f250 in TAGH [https://logbooks.jlab.org/entry/3940210] - no longer an issue (Sasha power-cycled the crate) | #* bad f250 in TAGH [https://logbooks.jlab.org/entry/3940210] - no longer an issue (Sasha power-cycled the crate) | ||
− | #* transmission - Hovanes will do AC scan when the beam is back after 10am | + | #* transmission - Hovanes will do AC scan when the beam is back after 10am - profiler doesn't lock has to be fixed at that time, as well |
# [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:] | # [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:] | ||
#* Down starting at 10am: for 1+ hours (Hall A changes to 4 passes) - FCAL items will be surveyed | #* Down starting at 10am: for 1+ hours (Hall A changes to 4 passes) - FCAL items will be surveyed |
Revision as of 09:41, 12 November 2021
Friday November 12
- Last 24h:
- Issues:
- bad f250 in TAGH [6] - no longer an issue (Sasha power-cycled the crate)
- transmission - Hovanes will do AC scan when the beam is back after 10am - profiler doesn't lock has to be fixed at that time, as well
- Plan:
- Down starting at 10am: for 1+ hours (Hall A changes to 4 passes) - FCAL items will be surveyed
- Continue production at 150nA on diamond
- Analysis update