− | =Monday | + | =Tuesday November 02= |
+ | #Last 24h: | ||
+ | #* Recorded 1090M+ events | ||
+ | #Issues: | ||
+ | #* Bleedthrough | ||
+ | # [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:] | ||
+ | #* Continue production at 200nA with the solenoid on. | ||
+ | #* Since Hall A cannot run at present, we are the priority hall. | ||
+ | #* Maintenance day '''shifted to Wed 11/03''' | ||
+ | #* Beam energy change planned for 11/05-11/07 | ||
+ | =Monday November 01= | ||
#Over the weekend: | #Over the weekend: | ||
#* Recorded 331M events from Fri, 8am till target was emptied. Then 1400M+ events with empty target until now | #* Recorded 331M events from Fri, 8am till target was emptied. Then 1400M+ events with empty target until now | ||
Line 24: | Line 34: | ||
#* Beam energy change planned for 11/05-11/07 | #* Beam energy change planned for 11/05-11/07 | ||
#* Hall A scheduled to come back online on Monday, 11/08 | #* Hall A scheduled to come back online on Monday, 11/08 | ||
− | =Friday | + | =Friday October 29= |
#Last 24h: | #Last 24h: | ||
#* Recorded 1090M+ events | #* Recorded 1090M+ events | ||
Line 43: | Line 53: | ||
#* Maintenance day '''shifted to Wed 11/03''' | #* Maintenance day '''shifted to Wed 11/03''' | ||
#* Beam energy change planned for 11/05-11/07; decision pending due to availability of Hall A | #* Beam energy change planned for 11/05-11/07; decision pending due to availability of Hall A | ||
− | =Thursday | + | =Thursday October 28= |
#Last 24h: | #Last 24h: | ||
#* Recorded 949M+ events | #* Recorded 949M+ events |
Revision as of 00:34, 2 November 2021
MCC whiteboard Meeting Bluejeans 660743227
Tuesday November 02
- Last 24h:
- Recorded 1090M+ events
- Issues:
- Bleedthrough
- Plan:
- Continue production at 200nA with the solenoid on.
- Since Hall A cannot run at present, we are the priority hall.
- Maintenance day shifted to Wed 11/03
- Beam energy change planned for 11/05-11/07
Monday November 01
- Over the weekend:
- Recorded 331M events from Fri, 8am till target was emptied. Then 1400M+ events with empty target until now
- Comment box on DAQ machine did not show up -> restarting DAQ brought it back. Missing comments for some runs recorded in logbook [1]
- Follow-up Re: Follow-up Re: TAGH scalers, roctagh2
- Target was emptied at 6:10pm Firday [2]
- BCAL noise at 10 o'clock
- Note on neutron background in Hall D
- Over the weekend, reference plots have been updated to reflect status with empty target [3]
- When we run with empty target, dont run AI for CDC HV. Stay with 2125V fixed value [4]
- power cycle of rocTAGH1, rocTAGH2, restart DAQ due to frozen TAGH scalers
- Spooky halloween shift - accelerator became unstable (lots of RF trips) sunday night [5]
- Target will be filled this morning (after the meeting). Chris C requested short access during filling to watch target interlock panel
- Issues:
-
BCAL noise at 10 o'clock - Bleedthrough
-
- Plan:
- Continue production at 200nA with the solenoid on.
- Since Hall A cannot run at present, we are the priority hall.
- Maintenance day on Wed 11/03 beam will be shut off at ~6am
- Hall D will go into controlled access for maintenance work (FCAL, ...?)
- Beam energy change planned for 11/05-11/07
- Hall A scheduled to come back online on Monday, 11/08
Friday October 29
- Last 24h:
- Recorded 1090M+ events
- Change out of C02
- RadCon replaced light bulb (was really broken) in our rapid access beacon with an LED bulb
- Access was necessary, but machine was actually down during that time
- RCDB web interface was unreachable, shift crew contacted administrator and the service was restarted
- HallC BCM calibration should not have affected us, but they use varying beam currents for that procedure, which may have changed bleedthrough during run 81620 (see [6])
- New wiki page with short-term guidance for shifters [7]
- Beam - RF Timing differences with different trigger types
- RAID beeping in DAQ room
- Issues:
- BCAL noise at 10 o'clock
- Bleedthrough
- Plan:
- Continue production at 200nA with the solenoid on.
- Since Hall A cannot run at present, we are the priority hall.
- Maintenance day shifted to Wed 11/03
- Beam energy change planned for 11/05-11/07; decision pending due to availability of Hall A
Thursday October 28
- Last 24h:
- Recorded 949M+ events
- Emergency Control box intermittent alarms
- TAGH scalers froze (roctagh2); TAGH1 and TAGH2 crates power cycled
- Some issues with starting root spy (see day shift summary)
- 2.5hrs downtime due to issue with magnet shunt module (has been replaced)
- Chris C (target) requested access to check heater power supply of the condenser [8].
- Our rapid access beacon is not working again (turning, but no light!)
- RadCon escorted Chris in and out of the hall.
- Rebinning issue in compton monitoring macro
- Issues:
- Rapid access beacon gives no light. The same failure happened 2 weeks ago, light bulb was replaced [9]
- Low energy tagger counters?
- BCAL noise at 10 o'clock
- Bleedthrough
- Plan:
- Continue production at 200nA with the solenoid on.
- Since Hall A cannot run at present, we are the priority hall.
- Hall C BCM calibration moved to today (Thursday) 2:30pm.
- Maintenance day planned for Tue 11/02
- Beam energy change planned for 11/05-11/07; decision pending due to availability of Hall A