(Created page with "== Meeting Time and Place == Thursday Jan 14, 2021, 2pm Bluejeans https://bluejeans.com/465620466 * Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S == Agenda == * Minut...") |
|||
Line 21: | Line 21: | ||
** Complete structural analysis | ** Complete structural analysis | ||
** Develop Detailed installation plan | ** Develop Detailed installation plan | ||
+ | ** Develop Design/operational/Maintenance Requirements | ||
+ | ** Modified US vacuum system | ||
+ | ** Solid target installation | ||
+ | |||
+ | == Minutes and Action Items == | ||
+ | * Request for ERR submitted | ||
+ | * We need to show that everything is in place for a successful experiment | ||
+ | ** Design status | ||
+ | ** Procurement schedule/status | ||
+ | ** Installation schedule | ||
+ | *** For installing prior to 2022 run - full detector then uninstall a portion to run Primex | ||
+ | *** For Installing in middle of 2022 run | ||
+ | ** Installation procedure | ||
+ | ** Manpower availability | ||
+ | ** Calibration and Analysis procedures | ||
+ | ** Need Safety documents | ||
+ | ** OSP | ||
+ | ** Installation procedure/HDlist | ||
+ | ** EESAD | ||
+ | ** COO | ||
+ | |||
+ | * Will use CDC Gas system and crates | ||
+ | * Signal cables needed | ||
+ | * Elton to write OSP | ||
+ | * Elton to start ERR web page (use DIRC as an example) | ||
+ | * Tim to update install schedule to show 2 scenarios | ||
+ | * Tim to Start installation plan | ||
+ | * Rory to get wire chambers working | ||
+ | * Tim and Stephanie to complete support stand drawing package |
Revision as of 16:58, 13 January 2021
Meeting Time and Place
Thursday Jan 14, 2021, 2pm Bluejeans https://bluejeans.com/465620466
- Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/December_17,_2020_CPP_Design_Meeting
- Readiness Review
- Schedule
Media:CPP_Schedule_before_primex.pdf Media:CPP_Schedule_after_primex.pdf
- Solid Pb target support and installation Media:CPP_Target.pdf
- Beam vacuum pipe needed for the experiment. (Target is located at z=1 cm, 64 cm upstream of nominal GlueX)
- Relocation of CDC FADC electronics for use with the muon chamber Media:CPP_Electronics_enclosure.pdf
- Review that there are no interferences for the new grounding shields for the muon chamber electronics.
- Design/Procurement status
- Things to work out
- Gas line manifold
- Complete structural analysis
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
- Modified US vacuum system
- Solid target installation
Minutes and Action Items
- Request for ERR submitted
- We need to show that everything is in place for a successful experiment
- Design status
- Procurement schedule/status
- Installation schedule
- For installing prior to 2022 run - full detector then uninstall a portion to run Primex
- For Installing in middle of 2022 run
- Installation procedure
- Manpower availability
- Calibration and Analysis procedures
- Need Safety documents
- OSP
- Installation procedure/HDlist
- EESAD
- COO
- Will use CDC Gas system and crates
- Signal cables needed
- Elton to write OSP
- Elton to start ERR web page (use DIRC as an example)
- Tim to update install schedule to show 2 scenarios
- Tim to Start installation plan
- Rory to get wire chambers working
- Tim and Stephanie to complete support stand drawing package