− | == Wednesday, Nov 28 at 8:45 ==
| + | |
− | # Comp Cal installation
| + | |
− | #* Completed at 6pm yesterday
| + | |
− | # First sight of beam (by Comp Cal): https://logbooks.jlab.org/entry/3633247
| + | |
− | # Swing and Overnight Running
| + | |
− | #* 15 nA on Al V-wire ([https://logbooks.jlab.org/entry/3633248 full running condition]).
| + | |
− | #* Lost beam around 2pm (due to radiation damaged valve position sensor).
| + | |
− | # FCAL is down:
| + | |
− | #* [https://logbooks.jlab.org/entry/3633312 Monitoring current draw on CAN bus] [Matt]
| + | |
− | #* Rapid access is arrange between 10am - noon.
| + | |
− | # Run Plan:
| + | |
− | #*
| + | |
− | # Cryo
| + | |
− | #* solenoid helium fill test this morning
| + | |