Difference between revisions of "Controls Meeting 15-May-2014"
From GlueXWiki
(Created page with "* Announcements * Minutes from previous meeting Controls Meeting 1-May-2014 * Gas system control in PLC (Dave) * EPICS GUIs for the gas system (Mike) * Status of TOF voltage ...") |
(→Action items) |
||
(6 intermediate revisions by 4 users not shown) | |||
Line 1: | Line 1: | ||
+ | = Agenda = | ||
+ | |||
* Announcements | * Announcements | ||
* Minutes from previous meeting [[Controls Meeting 1-May-2014]] | * Minutes from previous meeting [[Controls Meeting 1-May-2014]] | ||
− | * Gas system control in PLC (Dave) | + | * Gas system control in PLC [[Media:FDC_Gas.pptx]] (Dave) |
− | * EPICS GUIs for the gas system (Mike) | + | * EPICS GUIs for the gas system [[CDC/FDC_Gas_System_GUI]](Mike) |
− | * Status of TOF voltage controls (Nerses, Vanik) | + | * [[Status of TOF voltage controls]] (Nerses, Vanik) |
* Any other business | * Any other business | ||
+ | |||
+ | = Minutes = | ||
+ | |||
+ | Present: Dave, Mike, Nerses, Vanik, Orlando, Beni, Elton | ||
+ | |||
+ | ===Gas System=== | ||
+ | * Dave showed details of the gas system controls for CDC and FDC. | ||
+ | * Mike presented his EPICS GUIs for gas system control. | ||
+ | |||
+ | === TOF voltages === | ||
+ | * Vanik and Nerses are working on TOF voltage controls. | ||
+ | * Vanik showed preliminary control screens for TOF voltages. | ||
+ | |||
+ | |||
+ | = Action items = | ||
+ | * Dave needs to implement alarms on the supply pressure. | ||
+ | * Mike will implement some parameters that Dave can use to adjust the cycling of the pressure measurements. | ||
+ | * Mike will find a way to turn the gas off without changing the set-point (check if Brooks controllers allow the valve to be shut off). | ||
+ | * <strike>Beni wants to have a bottle at the T to run gas into CDC, Dave will set it up. </strike> | ||
+ | * <strike>Nerses and Vanik will finish the TOF voltages and start tagger hodoscope voltage controls. </strike> |
Latest revision as of 10:25, 28 May 2014
Agenda
- Announcements
- Minutes from previous meeting Controls Meeting 1-May-2014
- Gas system control in PLC Media:FDC_Gas.pptx (Dave)
- EPICS GUIs for the gas system CDC/FDC_Gas_System_GUI(Mike)
- Status of TOF voltage controls (Nerses, Vanik)
- Any other business
Minutes
Present: Dave, Mike, Nerses, Vanik, Orlando, Beni, Elton
Gas System
- Dave showed details of the gas system controls for CDC and FDC.
- Mike presented his EPICS GUIs for gas system control.
TOF voltages
- Vanik and Nerses are working on TOF voltage controls.
- Vanik showed preliminary control screens for TOF voltages.
Action items
- Dave needs to implement alarms on the supply pressure.
- Mike will implement some parameters that Dave can use to adjust the cycling of the pressure measurements.
- Mike will find a way to turn the gas off without changing the set-point (check if Brooks controllers allow the valve to be shut off).
-
Beni wants to have a bottle at the T to run gas into CDC, Dave will set it up. -
Nerses and Vanik will finish the TOF voltages and start tagger hodoscope voltage controls.