Difference between revisions of "GlueX Start Counter Meeting, April 3, 2014"
(→Communication Information) |
m (Text replacement - "www/halldweb1/" to "www/halldweb/") |
||
(4 intermediate revisions by the same user not shown) | |||
Line 8: | Line 8: | ||
# Announcements | # Announcements | ||
# Review [[GlueX Start Counter Meeting, March 20, 2014#Minutes|minutes from previous meeting]] | # Review [[GlueX Start Counter Meeting, March 20, 2014#Minutes|minutes from previous meeting]] | ||
− | # | + | # Detector Construction Status |
− | # Support | + | # Support Structure Construction Status |
=Communication Information= | =Communication Information= | ||
Line 32: | Line 32: | ||
==Slides== | ==Slides== | ||
− | Talks can be deposited in the directory <code>/group/halld/www/ | + | Talks can be deposited in the directory <code>/group/halld/www/halldweb/html/talks/2014-2Q</code> on the JLab CUE. This directory is accessible from the web at https://halldweb.jlab.org/talks/2014-2Q/ . |
+ | |||
+ | = Minutes = | ||
+ | |||
+ | Present: | ||
+ | * '''FIU''': Werner Boeglin, Eric Pooser | ||
+ | * '''JLab''': Eugene Chudakov, Mark Ito (chair), Chuck Hutton, Tim Whitlatch | ||
+ | |||
+ | == Detector Construction Status == | ||
+ | |||
+ | Eric gave us the update. | ||
+ | |||
+ | Eljen has made fifty bent scintillator bars. They arrived at McNeal yesterday. The team at McNeal is meeting to detail plans for machining. They will start in a week and the process should take about a week or two. The hope is to receive the counters at FIU at the end of April. Testing rate is 5 per day. | ||
+ | |||
+ | The mis-alignment study continues. There is an undergraduate working on it. | ||
+ | |||
+ | Fabrication of the assembly jig will start next week. That should take a week or two. | ||
+ | |||
+ | Final construction should start in the middle of May. | ||
+ | |||
+ | == Support structure construction status == | ||
+ | |||
+ | The Rohacell block are being glued now. Tom Carstens is doing that. | ||
+ | |||
+ | We looked at the final drawings for the support structure. They are now all out for signatures. | ||
+ | |||
+ | Werner reminded us that we plan to delay drilling holes in the second aluminum collar, in case some problem is identified with the hole locations in the first one. | ||
+ | |||
+ | == Readiness Review == | ||
+ | |||
+ | Mid-May looks to be a likely time for a Readiness Review. We also need to review plans for having Nick Sandoval travel to FIU to set-up the electronics. | ||
+ | |||
+ | == BlueJeans== | ||
+ | |||
+ | We used BlueJeans for this meeting without major incident, which is good. |
Latest revision as of 17:30, 31 March 2015
GlueX Start Counter Meeting
Thursday, April 3, 2014
10:00 am EDT
JLab: CEBAF Center F326
Contents
Agenda
- Announcements
- Review minutes from previous meeting
- Detector Construction Status
- Support Structure Construction Status
Communication Information
Video Conferencing
BlueJeans
We will try BlueJeans for this meeting. Remember that log in is with your JLab username and password.
The BlueJeans Meeting ID is 997 409 529.
Given the late notice we may have to fall back to the old ESNet system. I've retained information for that below, just in case.
Fall-Back Information
Slides
Talks can be deposited in the directory /group/halld/www/halldweb/html/talks/2014-2Q
on the JLab CUE. This directory is accessible from the web at https://halldweb.jlab.org/talks/2014-2Q/ .
Minutes
Present:
- FIU: Werner Boeglin, Eric Pooser
- JLab: Eugene Chudakov, Mark Ito (chair), Chuck Hutton, Tim Whitlatch
Detector Construction Status
Eric gave us the update.
Eljen has made fifty bent scintillator bars. They arrived at McNeal yesterday. The team at McNeal is meeting to detail plans for machining. They will start in a week and the process should take about a week or two. The hope is to receive the counters at FIU at the end of April. Testing rate is 5 per day.
The mis-alignment study continues. There is an undergraduate working on it.
Fabrication of the assembly jig will start next week. That should take a week or two.
Final construction should start in the middle of May.
Support structure construction status
The Rohacell block are being glued now. Tom Carstens is doing that.
We looked at the final drawings for the support structure. They are now all out for signatures.
Werner reminded us that we plan to delay drilling holes in the second aluminum collar, in case some problem is identified with the hole locations in the first one.
Readiness Review
Mid-May looks to be a likely time for a Readiness Review. We also need to review plans for having Nick Sandoval travel to FIU to set-up the electronics.
BlueJeans
We used BlueJeans for this meeting without major incident, which is good.