Difference between revisions of "November 30, 2007 Software"
(→Agenda) |
|||
Line 30: | Line 30: | ||
==Minutes== | ==Minutes== | ||
− | Attendees: ' | + | Attendees: David L. (chair), Elliott W., Eugene C., Elke A., Simon T., Tim W., Mark I. |
+ | |||
+ | Attending remotely: Curtis M., Vardan G., Franx K., Richard J., Matt B., Zisis P., Matt S., Benni Z. | ||
+ | |||
+ | |||
+ | ===Offline Software Needs for CD-3=== | ||
+ | The entire meeting was devoted to reviewing the status of the simulation and reconstruction | ||
+ | software and determining what needs to be done prior to CD-3. David showed some slides | ||
+ | that led to some discussion and eventual consensus on the list of the most important tasks | ||
+ | and who the responsible parties are. David agreed to update the action items tracker excel | ||
+ | sheet on Elke's homepage (this since been done). The items added were: | ||
+ | |||
+ | {| border="1" | ||
+ | |- | ||
+ | |bgcolor="yellow"|Responsible || bgcolor ="yellow"|Task || bgcolor ="yellow"|Target Date | ||
+ | |- | ||
+ | |Jones, Taylor, Lawrence || Complete implementation of v4 geometry || 12/7/07 | ||
+ | |- | ||
+ | |Indiana ||Check forward calorimetry gap || 1/18/08 | ||
+ | |- | ||
+ | |Uconn, Indiana || If needed, implement gap calorimeter in simulation and test || 2/8/08 | ||
+ | |- | ||
+ | |Lawrence || Complete development of track finding || 12/21/07 | ||
+ | |- | ||
+ | |Lawrence, Taylor, Ito || Compare baseline cathodes design with wires only design || 1/11/08 | ||
+ | |- | ||
+ | | || Map single particle acceptance/efficiency/resolutions for all detector system || 5/23/08 | ||
+ | |- | ||
+ | | || Map "gold channel" acceptance/efficiency/resolutions for all detector systems || 5/23/08 | ||
+ | |- | ||
+ | |Lanzhau || Level 1 trigger simulations || 4/25/08 | ||
+ | |- | ||
+ | |Ito || Understand backgrounds || 1/11/08 | ||
+ | |- | ||
+ | |Taylor || FDC Lorentz correction in reconstruction || 1/15/08 | ||
+ | |- | ||
+ | |? || Overall review of PID with new geometry || | ||
+ | |- | ||
+ | |Lawrence || Optimize overall tracking for combined detectors || 2/29/08 | ||
+ | |- | ||
+ | |Lawrence || CDC layer optimization || 5/30/08 | ||
+ | |- | ||
+ | |Regina || BCAL layering stand alone simulations || 2/1/08 | ||
+ | |} | ||
==[[Action Items From Hall-D Software Meetings|Action items]]== | ==[[Action Items From Hall-D Software Meetings|Action items]]== |
Latest revision as of 22:11, 5 December 2007
Contents
Agenda
- Review minutes from November 13, 2007 Software meeting
- Offline Software Needs for CD-3 (Hall D Project Action Item Tracker)
- Action Items
Participating
Location
The meeting will be at 2:00pm in Cebaf Center F326-327.
Telephone
To connect by telephone: 1.) dial:
800-377-8846 : US 888-276-7715 : Canada 302-709-8424 : International
2.) enter participant code: 39527048# (remember the "#")
Video Conferencing
We will attempt an ESNet connection for this meeting using the following number:
8542553
We have a reasonable expectation that this will work.
Minutes
Attendees: David L. (chair), Elliott W., Eugene C., Elke A., Simon T., Tim W., Mark I.
Attending remotely: Curtis M., Vardan G., Franx K., Richard J., Matt B., Zisis P., Matt S., Benni Z.
Offline Software Needs for CD-3
The entire meeting was devoted to reviewing the status of the simulation and reconstruction software and determining what needs to be done prior to CD-3. David showed some slides that led to some discussion and eventual consensus on the list of the most important tasks and who the responsible parties are. David agreed to update the action items tracker excel sheet on Elke's homepage (this since been done). The items added were:
Responsible | Task | Target Date |
Jones, Taylor, Lawrence | Complete implementation of v4 geometry | 12/7/07 |
Indiana | Check forward calorimetry gap | 1/18/08 |
Uconn, Indiana | If needed, implement gap calorimeter in simulation and test | 2/8/08 |
Lawrence | Complete development of track finding | 12/21/07 |
Lawrence, Taylor, Ito | Compare baseline cathodes design with wires only design | 1/11/08 |
Map single particle acceptance/efficiency/resolutions for all detector system | 5/23/08 | |
Map "gold channel" acceptance/efficiency/resolutions for all detector systems | 5/23/08 | |
Lanzhau | Level 1 trigger simulations | 4/25/08 |
Ito | Understand backgrounds | 1/11/08 |
Taylor | FDC Lorentz correction in reconstruction | 1/15/08 |
? | Overall review of PID with new geometry | |
Lawrence | Optimize overall tracking for combined detectors | 2/29/08 |
Lawrence | CDC layer optimization | 5/30/08 |
Regina | BCAL layering stand alone simulations | 2/1/08 |