Difference between revisions of "February 24, 2012 Design Meeting"
From GlueXWiki
(Created page with "Friday Feb 24, 2012 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 231 == Agenda == * ESH&Q minute - Pressure systems * Announcements ** Health plan open enr...") |
(→Agenda) |
||
(7 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
== Agenda == | == Agenda == | ||
− | * ESH&Q minute - Pressure systems | + | * ESH&Q minute - Paul? |
+ | ** Manager's Safety mtg http://www.jlab.org/memo/2012_managers_meeting.html. | ||
+ | ** Pressure systems https://jlabdoc.jlab.org/docushare/dsweb/View/Collection-1414 | ||
* Announcements | * Announcements | ||
** Health plan open enrollment closes next week | ** Health plan open enrollment closes next week | ||
Line 9: | Line 11: | ||
* CAD update | * CAD update | ||
− | * FDC construction update | + | * Overall status from collaboration meeting [[Media:Feb_Status.pdf]] |
+ | * FDC construction update | ||
* Tagger update | * Tagger update | ||
* Target update | * Target update | ||
Line 17: | Line 20: | ||
* Controls | * Controls | ||
* Engineering tools folder M:\halld_engineering\engineering tools | * Engineering tools folder M:\halld_engineering\engineering tools | ||
− | * Installation Schedule [[Media: | + | * FDC installation tooling |
+ | * Installation Schedule [[Media:SAD_Installation1.pdf]] | ||
+ | * Engineering tasks M:\halld_engineering\Manpower-schedule | ||
* Piping systems B31.3 vs B31.9 [[Media:B31-3_vs_B31-9.pdf]] | * Piping systems B31.3 vs B31.9 [[Media:B31-3_vs_B31-9.pdf]] | ||
==Outstanding Action Items== | ==Outstanding Action Items== |
Latest revision as of 08:46, 24 February 2012
Friday Feb 24, 2012 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 231
Agenda
- ESH&Q minute - Paul?
- Manager's Safety mtg http://www.jlab.org/memo/2012_managers_meeting.html.
- Pressure systems https://jlabdoc.jlab.org/docushare/dsweb/View/Collection-1414
- Announcements
- Health plan open enrollment closes next week
- Space - 4th floor in March Media:floor-plan_4th_floor.pdf
- CAD update
- Overall status from collaboration meeting Media:Feb_Status.pdf
- FDC construction update
- Tagger update
- Target update
- Electrical - Giles
- Platforms
- Solenoid interface
- Controls
- Engineering tools folder M:\halld_engineering\engineering tools
- FDC installation tooling
- Installation Schedule Media:SAD_Installation1.pdf
- Engineering tasks M:\halld_engineering\Manpower-schedule
- Piping systems B31.3 vs B31.9 Media:B31-3_vs_B31-9.pdf