Difference between revisions of "Nov 15, 2011 Readout"
From GlueXWiki
(→Minutes) |
m (Text replacement - "/halldweb1.jlab.org/" to "/halldweb.jlab.org/") |
||
(One intermediate revision by one other user not shown) | |||
Line 27: | Line 27: | ||
# USM Update | # USM Update | ||
#* [http://atlasusr.fis.utfsm.cl:8000/ USM Web Interface to DB] | #* [http://atlasusr.fis.utfsm.cl:8000/ USM Web Interface to DB] | ||
− | #* [https:// | + | #* [https://halldweb.jlab.org/wiki/images/f/fc/HallD15Nov2011.pdf Progress on microscope inspection station and PDE station] |
− | #* [https:// | + | #* [https://halldweb.jlab.org/wiki/images/7/76/Test1_DSRL_10mppc_setup_IMG_4006_-_copia.JPG high-resolution photo of MPPC] |
#* Discussion of [[Readiness Review: Testing of light sensors for Bcal]] | #* Discussion of [[Readiness Review: Testing of light sensors for Bcal]] | ||
# SiPM update | # SiPM update | ||
Line 47: | Line 47: | ||
##* Shipping of 30 first-article units from JLab. Units are ready, but we are trying to make sure all the paperwork is in order before shipment. | ##* Shipping of 30 first-article units from JLab. Units are ready, but we are trying to make sure all the paperwork is in order before shipment. | ||
## [http://atlasusr.fis.utfsm.cl:8000/ USM Web Interface to DB] | ## [http://atlasusr.fis.utfsm.cl:8000/ USM Web Interface to DB] | ||
− | ## [https:// | + | ## [https://halldweb.jlab.org/wiki/images/f/fc/HallD15Nov2011.pdf Progress on microscope inspection station and PDE station] |
##* Test station with camera takes pictures with good resolution | ##* Test station with camera takes pictures with good resolution | ||
##* Station 2 (PDE) measurements was reviewed | ##* Station 2 (PDE) measurements was reviewed | ||
Line 55: | Line 55: | ||
##* Eugene: Asked about cross talk. The question will be passed on to those doing the work. Also noted that materials in dark box (especially reflective ones) should be painted black. | ##* Eugene: Asked about cross talk. The question will be passed on to those doing the work. Also noted that materials in dark box (especially reflective ones) should be painted black. | ||
##* Elton: Asked about how the absolute calibration for the light source is obtained (required for the PDE). [Note: Regina does the measurements with the Hamamatsu laser and a calibrated diode]. | ##* Elton: Asked about how the absolute calibration for the light source is obtained (required for the PDE). [Note: Regina does the measurements with the Hamamatsu laser and a calibrated diode]. | ||
− | ## [https:// | + | ## [https://halldweb.jlab.org/wiki/images/7/76/Test1_DSRL_10mppc_setup_IMG_4006_-_copia.JPG high-resolution photo of MPPC] |
#* Discussion of [[Readiness Review: Testing of light sensors for Bcal]] | #* Discussion of [[Readiness Review: Testing of light sensors for Bcal]] | ||
#* Will believes that they are "sufficiently ready" for the Readiness Review. He will review with Sergey status and confirm readiness date. | #* Will believes that they are "sufficiently ready" for the Readiness Review. He will review with Sergey status and confirm readiness date. | ||
# SiPM update | # SiPM update | ||
# Electrical/cooling (Elton) | # Electrical/cooling (Elton) | ||
+ | #* Mechanical pieces already arrived or on order. | ||
+ | #* Electrical boards should be ordered before the holidays. | ||
# Geometry and light guides | # Geometry and light guides | ||
#* Order placed with USM. They have ordered material, but fabrication has not started. | #* Order placed with USM. They have ordered material, but fabrication has not started. |
Latest revision as of 06:05, 1 April 2015
Teleconference Time: 11:00 a.m. EST
- ESNET 8542553 and EVO session
- JLab Phone: in CC F326 is 757-269-6337 (usual room)
- JLab Phone in CC L207 is 757-269-7084
- Phone in the Regina Videoconference Suite is 306-585-4204
- Athens Phone: in Christina's office is 011-30-210-727-6947
- Phone:
- +1-866-740-1260 : US and Canada
- +1-303-248-0285 : International
- then use participant code: 3421244# (the # is needed when using the phone)
- OR from www.readytalk.com type access code 3421244 into "join a meeting" without the # (you need java plugin)
Contents
Items for followup from previous meeting
-
Will confirm delivery dates of SiPMs with Hamamatsu. -
Based on SiPM delivery dates, schedule the Readiness Review at USM.Tentative date is Dec 15 -
Elton to check availability of SiPMs and electronics to loan to AthensRequest is in, but not highest priority -
Elton to update light guide specifications to change haze < 2%Sent updated specifications to USM - Yi and USM coordinate working on common interfaces to the data bases.
Documents to Review
Tentative Agenda
- Announcements
- Review of Action Items
- Monitoring Update (Athens)
- USM Update
- SiPM update
- Electrical/cooling (Elton)
- Geometry and light guides
- Simulations
- Other
Minutes
Attending: Christina, Pavlos, George (Athens); George, Zisis, Andrei (UofR); Elton, Yi, John, Eugene (JLab); Will (USM).
- Announcements
- Review of Action Items
- Monitoring Update (Athens)
- USM Update
- Schedule for deliveries
- Expected from Hamamatsu Dec 6, but payment schedule needs to be clarified.
- Shipping of 30 first-article units from JLab. Units are ready, but we are trying to make sure all the paperwork is in order before shipment.
- USM Web Interface to DB
- Progress on microscope inspection station and PDE station
- Test station with camera takes pictures with good resolution
- Station 2 (PDE) measurements was reviewed
- Wooden dark box for station. Uses JLab board. LED illuminates clear fiber, which feeds a solid cylinder to mix light and output fibers (on the same side as input) provide relatively uniform light to individual cells of SiPM.
- Light uniformity times cell uniformity is about 15-20%. This test used the SiPMs with 20 V in reverse bias mode. Variations from quadrant to quadrant are major, but little variation within quadrant. [Note that both UofR and JLab see variations within a quadrant].
- John: Suggests that the sensor be rotated to check variations among quadrants
- Eugene: Asked about cross talk. The question will be passed on to those doing the work. Also noted that materials in dark box (especially reflective ones) should be painted black.
- Elton: Asked about how the absolute calibration for the light source is obtained (required for the PDE). [Note: Regina does the measurements with the Hamamatsu laser and a calibrated diode].
- high-resolution photo of MPPC
- Discussion of Readiness Review: Testing of light sensors for Bcal
- Will believes that they are "sufficiently ready" for the Readiness Review. He will review with Sergey status and confirm readiness date.
- Schedule for deliveries
- SiPM update
- Electrical/cooling (Elton)
- Mechanical pieces already arrived or on order.
- Electrical boards should be ordered before the holidays.
- Geometry and light guides
- Order placed with USM. They have ordered material, but fabrication has not started.
- Gluing tests continue with plexiglass and lead separately.
- Regina has shipped 4 Bcal slices, expected by Friday.
- Eugene: We should check gluing tests through temperature cycles.
- Note that KLOE glued their modules vertically using BC-600, which is the same glue used for the matrix.
- Simulations
- Other