Line 11: | Line 11: | ||
* DOE review 28-Sep - George, Elliott | * DOE review 28-Sep - George, Elliott | ||
** final status for Glenn's talk | ** final status for Glenn's talk | ||
− | ** Conduct of Operations | + | ** preparation for visit to Test Lab by reviewers |
+ | * Conduct of Operations - Josh, Elliott | ||
+ | ** results of Wed meeting | ||
* OSP documents and review - Elliott, George | * OSP documents and review - Elliott, George | ||
** what is left to do? | ** what is left to do? | ||
Line 19: | Line 21: | ||
** when do we give two weeks notice to Errol? | ** when do we give two weeks notice to Errol? | ||
* Test plan - Josh | * Test plan - Josh | ||
+ | ** addition of check valve and relief valve in lead flow system | ||
* Magnet power supply and interlock commissioning - Cody | * Magnet power supply and interlock commissioning - Cody | ||
** latest status | ** latest status | ||
+ | ** adding a shunt to the interlock system | ||
* Controls racks - Scot | * Controls racks - Scot | ||
** strain gauge interlock | ** strain gauge interlock | ||
Line 29: | Line 33: | ||
** guard shack | ** guard shack | ||
** what's left? | ** what's left? | ||
− | ** backup PLC programmer | + | ** backup PLC programmer, file locations, license key |
** tutorial? | ** tutorial? | ||
− | * EPICS <--> PLC communications - | + | * EPICS <--> PLC communications - Hovanes |
− | ** PV list from Jonathan Creel | + | ** PV list from Jonathan Creel and PLC tags |
+ | ** connection to guard shack | ||
** under what circumstances do we notify the guard shack? | ** under what circumstances do we notify the guard shack? | ||
− | * HMI and [http://halldeweb1.jlab.org/user/web/ | + | * HMI and [http://halldeweb1.jlab.org/user/web/plc_urls.html EWEB programming] - Yi, Hovanes |
** Josh's screens | ** Josh's screens | ||
** current status | ** current status | ||
** tutorial? | ** tutorial? | ||
* Coil repair status - George | * Coil repair status - George | ||
+ | * Solenoid review 25-26 Oct | ||
* Preparations for testing next coil - George, Elliott | * Preparations for testing next coil - George, Elliott | ||
** update P&I | ** update P&I | ||
Line 46: | Line 52: | ||
** downstream yoke spacers | ** downstream yoke spacers | ||
** controls racks rewiring | ** controls racks rewiring | ||
+ | |||
+ | |||
+ | |||
+ | |||
+ | '''Lehman Review Committee Visit''' | ||
+ | |||
+ | * the visit is scheduled for 1pm -2pm Wed 29-Sep | ||
+ | * currently there are five visitors on Sherry's list, there may be more | ||
+ | * Tom will have the area ready for visitors by Mon afternoon 27-Sep | ||
+ | * they will either walk or ride to the Test Lab, not sure yet | ||
+ | * Tom and I will meet them near the rollup door to the high bay | ||
+ | * Tom or I will give them a very short safety briefing | ||
+ | * PPE is not required to visit the coil test area | ||
+ | * the Test Lab is an industrial building, so there are trip hazards all over the place | ||
+ | * Tom will eliminate trip hazards in our area as best he can | ||
+ | * our area is designated ODH 0, which I think means that visitors are allowed if they are chaperoned | ||
+ | * they will be asked not to wander away from the areas we take them to | ||
+ | * they will be asked to be careful where they put their hands, heads, feet, and any other valuable body part | ||
+ | |||
+ | then: | ||
+ | |||
+ | * I (or Eugene? or Elton?) will lead them to the coil test apparatus and give them a brief introduction as to what | ||
+ | they are looking at, how it works, a little history, etc. I'm thinking 5 min or less. | ||
+ | * after the intro they can ask questions, break off to talk with particular experts, whatever. I assume Eugene, | ||
+ | Elton, George, and Tim (Josh B, too?) will be there to answer questions. |
Latest revision as of 21:54, 22 September 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 23-Sep-2010 9:30am ARC 428
Agenda
- DOE review 28-Sep - George, Elliott
- final status for Glenn's talk
- preparation for visit to Test Lab by reviewers
- Conduct of Operations - Josh, Elliott
- results of Wed meeting
- OSP documents and review - Elliott, George
- what is left to do?
- when can/must we turn everything in?
- Installation status
- what's left?
- when do we give two weeks notice to Errol?
- Test plan - Josh
- addition of check valve and relief valve in lead flow system
- Magnet power supply and interlock commissioning - Cody
- latest status
- adding a shunt to the interlock system
- Controls racks - Scot
- strain gauge interlock
- UPS interlock
- anything else?
- PLC programming/testing status - Mark W
- UPS interlock
- guard shack
- what's left?
- backup PLC programmer, file locations, license key
- tutorial?
- EPICS <--> PLC communications - Hovanes
- PV list from Jonathan Creel and PLC tags
- connection to guard shack
- under what circumstances do we notify the guard shack?
- HMI and EWEB programming - Yi, Hovanes
- Josh's screens
- current status
- tutorial?
- Coil repair status - George
- Solenoid review 25-26 Oct
- Preparations for testing next coil - George, Elliott
- update P&I
- splices
- yoke location
- piping adaptors
- downstream yoke spacers
- controls racks rewiring
Lehman Review Committee Visit
- the visit is scheduled for 1pm -2pm Wed 29-Sep
- currently there are five visitors on Sherry's list, there may be more
- Tom will have the area ready for visitors by Mon afternoon 27-Sep
- they will either walk or ride to the Test Lab, not sure yet
- Tom and I will meet them near the rollup door to the high bay
- Tom or I will give them a very short safety briefing
- PPE is not required to visit the coil test area
- the Test Lab is an industrial building, so there are trip hazards all over the place
- Tom will eliminate trip hazards in our area as best he can
- our area is designated ODH 0, which I think means that visitors are allowed if they are chaperoned
- they will be asked not to wander away from the areas we take them to
- they will be asked to be careful where they put their hands, heads, feet, and any other valuable body part
then:
- I (or Eugene? or Elton?) will lead them to the coil test apparatus and give them a brief introduction as to what
they are looking at, how it works, a little history, etc. I'm thinking 5 min or less.
- after the intro they can ask questions, break off to talk with particular experts, whatever. I assume Eugene,
Elton, George, and Tim (Josh B, too?) will be there to answer questions.