Difference between revisions of "Run Planning Meeting Notes, August 11- August 17, 2022"
From GlueXWiki
(→Plans) |
|||
(62 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
+ | Back to [[Run Coordination Meetings:Summer2022]] | ||
+ | |||
+ | Meeting are via ZoomGov: [https://jlab-org.zoomgov.com/j/1601990060?pwd=TUtwTGszMFg5bjhwdC9nU0IvREUzZz09 connect] (Meeting ID: 160 199 0060 / Passcode 8394) | ||
+ | |||
+ | [https://cebaf.jlab.org/files/ops/accboard/ MCC whiteboard] | ||
+ | |||
+ | [https://halldweb.jlab.org/online/whiteboard/ Hall D counting room white board] | ||
+ | |||
+ | [https://docs.google.com/spreadsheets/d/1sdluzy7p5vnlhw9AWJHBrYbXKTBet45o4den4zWX9dc/edit#gid=1855021251 Spreadsheet with list of runs] | ||
+ | |||
= Thursday August 11 = | = Thursday August 11 = | ||
=== Past 24 hours === | === Past 24 hours === | ||
Line 28: | Line 38: | ||
= Friday August 12 = | = Friday August 12 = | ||
=== Past 24 hours === | === Past 24 hours === | ||
− | * Beam off 630 am - ?? pm for maintenance day | + | * Beam off Thu 630 am - ?? pm for maintenance day |
− | * ~ 9 am access to tagger hall by Beni to reset TAGH HV crate | + | * ~ 9 am access to tagger hall by Beni to reset TAGH HV crate; OK now |
* ramped down solenoid for cry work (Tim) | * ramped down solenoid for cry work (Tim) | ||
+ | |||
+ | * resume prodcution data Friday 3:18 am | ||
=== Shift Reports === | === Shift Reports === | ||
Line 39: | Line 51: | ||
=== Reports === | === Reports === | ||
+ | * Beni reset the TAGH HV crate; it's communicating again ([https://logbooks.jlab.org/entry/4027510]) | ||
+ | * Malte changed 2 FCAL bases ([https://logbooks.jlab.org/entry/4027538], [https://logbooks.jlab.org/entry/4027579]) | ||
+ | * The filter material (Molecular Sieve) Assy. for the Cryomech cold compressor in Hall-D has been completed by target group | ||
+ | * Tim also reports that compressor swap is complete; not sure whether that refers to the target group's work? | ||
+ | * Beam delivary after maintenance day delayed until ??? due to a leak in magnet LCW hose in NL. | ||
+ | |||
=== Issues === | === Issues === | ||
=== Plans === | === Plans === | ||
+ | * Continue with prodcution data on Pb through the weekend. | ||
+ | * Plan for TAC run on Monday, when Hall C installs their aerogel. | ||
− | = Monday August 14 = | + | = Monday August 15 = |
+ | === Past 72 Hours Summary === | ||
+ | Time lost in hall mainly due to beam tuning; Hall C bleedthrough to B is still an issue. | ||
+ | |||
+ | There is some chatter this morning about position locks [https://logbooks.jlab.org/entry/4029138] | ||
+ | |||
+ | === Plan for Monday through Thursday === | ||
+ | * Monday: [https://logbooks.jlab.org/entry/4028848 Hall C will turn off beam at 7 am] to get ready for aerogel installation at 8 am. Is supposed to take about 6 hours. | ||
+ | * Access to hall at 7 am to move target to empty position. | ||
+ | * Sasha will try to make it in by 7:30 am to start TAC measurement. | ||
+ | * Upon completion of TAC measurement resume production on empty target | ||
+ | * [https://logbooks.jlab.org/entry/4028848 Hall C pass change now scheduled for Wednesday]. But C now is considering changing Tuesday. Decision will be made at noon. | ||
+ | * Thursday 7 am end of run; start installation period for PrimeX | ||
+ | |||
+ | == Friday: Day through Owl == | ||
+ | * at 7:45 am meeting Hall B complained about bleedthrough from C; optimizing the machine led to considerable downtime during the day. | ||
+ | * at 12 pm MCC starts tuning | ||
+ | <!-- * [https://logbooks.jlab.org/entry/4027490 Program Deputy summary] --> | ||
+ | * Otherwise running on Pb target (30 nA) | ||
+ | |||
+ | {| class=wikitable | ||
+ | |+ Recorded BTA | ||
+ | |- | ||
+ | ! Shift | ||
+ | ! ABU | ||
+ | ! BANU | ||
+ | ! BNA | ||
+ | ! ER | ||
+ | |- | ||
+ | ! 8/12 Day | ||
+ | | 4.24 h || 3.3 min || 3.70 h || 8 h | ||
+ | |- | ||
+ | !8/12 Swing | ||
+ | | 2.97 h || 1.40 h || 3.63 h || 8 h | ||
+ | |- | ||
+ | !8/13 Owl | ||
+ | | 6.49 h || 0.30 h || 1.20 h || 7.93 h | ||
+ | |- | ||
+ | |- | ||
+ | ! Total | ||
+ | | 13.70 h || 1.76 h || 8.53 h || 23.93 h | ||
+ | |} | ||
+ | |||
+ | Shift Reports | ||
+ | * [https://logbooks.jlab.org/entry/4027930 Day shift summary] | ||
+ | * [https://logbooks.jlab.org/entry/4028084 Swing shift summary] | ||
+ | * [https://logbooks.jlab.org/entry/4028182 Owl shift summary] | ||
+ | * [https://logbooks.jlab.org/entry/4028265 Eraly riser shift summary] | ||
+ | |||
+ | Reports | ||
+ | * Harp scans: [https://logbooks.jlab.org/entry/4028157 IHA5C11], [https://logbooks.jlab.org/entry/4028158 IHA5C11B], [https://logbooks.jlab.org/entry/4028163 our harp], [https://logbooks.jlab.org/entry/4028172 convergence fits]; looks very good, much better than scans from last night. | ||
+ | |||
+ | Issues | ||
+ | * | ||
+ | |||
+ | Plans | ||
+ | * | ||
+ | |||
+ | == Saturday == | ||
+ | |||
+ | {| class=wikitable | ||
+ | |+ Recorded BTA | ||
+ | |- | ||
+ | ! Shift | ||
+ | ! ABU | ||
+ | ! BANU | ||
+ | ! BNA | ||
+ | ! ER | ||
+ | |- | ||
+ | ! 8/13 Day | ||
+ | | 6.16 h || 0.14 h || 1.70 h || 7.87 h | ||
+ | |- | ||
+ | !8/13 Swing | ||
+ | | 4.80 h || 0.38 h || 2.82 h || 7.93 h | ||
+ | |- | ||
+ | !8/14 Owl | ||
+ | | 6.75 h || 0.29 h || 0.97 h || 7.9 h | ||
+ | |- | ||
+ | |- | ||
+ | ! Total | ||
+ | | 17.71 h || 0.81 h || 5.49 h || 23.70 h | ||
+ | |} | ||
+ | |||
+ | Shift Reports | ||
+ | * [https://logbooks.jlab.org/entry/4028347 Day shift summary] | ||
+ | * [https://logbooks.jlab.org/entry/4028427 Swing shift summary] | ||
+ | * [https://logbooks.jlab.org/entry/4028517 Owl shift summary] | ||
+ | * [https://logbooks.jlab.org/entry/4028608 Early riser shift summary] | ||
+ | |||
+ | Issues | ||
+ | * one locked up FCAL base; shift crew followed reset procedure | ||
+ | |||
+ | == Sunday == | ||
+ | {| class=wikitable | ||
+ | |+ Recorded BTA | ||
+ | |- | ||
+ | ! Shift | ||
+ | ! ABU | ||
+ | ! BANU | ||
+ | ! BNA | ||
+ | ! ER | ||
+ | |- | ||
+ | ! 8/14 Day [https://logbooks.jlab.org/entry/4028810] | ||
+ | | 6.46 h || 0.21 h || 1.33 h || 7.82 h | ||
+ | |- | ||
+ | !8/14 Swing [https://logbooks.jlab.org/entry/4029010] | ||
+ | | 5.62 h || 0.39 h || 2.00 h || 7.95 h | ||
+ | |- | ||
+ | !8/15 Owl [https://logbooks.jlab.org/entry/4029162] | ||
+ | | 6.24 h || 0.46 h || 1.30 h || 7.58 h | ||
+ | |- | ||
+ | |- | ||
+ | ! Total | ||
+ | | 18.32 h || 1.06 h || 4.63 h || 23.35 h | ||
+ | |} | ||
+ | |||
+ | Shift reports | ||
+ | *[https://logbooks.jlab.org/entry/4028690 Day shift summary] | ||
+ | *[https://logbooks.jlab.org/entry/4028824 Swing shift summary] | ||
+ | *[https://logbooks.jlab.org/entry/4028972 Owl shift summary] | ||
+ | * Early Riser shift summary | ||
+ | |||
+ | = Tuesday August 16 = | ||
=== Past 24 hours === | === Past 24 hours === | ||
+ | * We did a TAC run while Hall C was installing their aerogel | ||
+ | * Otherwise production running on empty target | ||
+ | |||
+ | === Shift Reports === | ||
+ | * [https://logbooks.jlab.org/entry/4029190 Day shift summaries] | ||
+ | * [https://logbooks.jlab.org/entry/4029362 Swing shift summary] | ||
+ | * [https://logbooks.jlab.org/entry/4029514 Owl shift summary] | ||
+ | * [https://logbooks.jlab.org/entry/4029604 Early Riser shift summary] | ||
+ | {| class=wikitable | ||
+ | |+ Recorded BTA | ||
+ | |- | ||
+ | ! Shift | ||
+ | ! ABU | ||
+ | ! BANU | ||
+ | ! BNA | ||
+ | ! ER | ||
+ | |- | ||
+ | ! 8/15 Day [https://logbooks.jlab.org/entry/4029776] | ||
+ | | 6.15 h || 0.78 h || 1.07 h || 8.0 h | ||
+ | |- | ||
+ | !8/15 Swing [https://logbooks.jlab.org/entry/4029778] | ||
+ | | 5.89 h || 0.36 h || 1.75 h || 7.77 h | ||
+ | |- | ||
+ | !8/16 Owl [https://logbooks.jlab.org/entry/4029698] | ||
+ | | 3.98 h || 0.12 h || 3.90 h || 7.88 h | ||
+ | |- | ||
+ | |- | ||
+ | ! Total | ||
+ | | h || h || h || h | ||
+ | |} | ||
+ | |||
+ | === Reports === | ||
+ | [https://logbooks.jlab.org/entry/4029440 Sasha did a TAC run] | ||
+ | |||
+ | === Issues === | ||
+ | * Excursions of AC.y beam position still ongoing, but less frequent | ||
+ | ** [https://logbooks.jlab.org/entry/4029566 Followup log entry] | ||
+ | ** [https://logbooks.jlab.org/entry/4029675 strip chart 6-7 am] | ||
+ | ** [https://logbooks.jlab.org/entry/4029659 5-6 am] | ||
+ | ** [https://logbooks.jlab.org/entry/4029634 4-5 am] | ||
+ | ** [https://logbooks.jlab.org/entry/4029521 7:30 pm - 10:30 pm] | ||
+ | * The acceptable tolerance in 0.2 mm from nominal; so, most of these blips are to far. | ||
+ | |||
+ | === Plans === | ||
+ | * Continue with prodcution data on empty target through Thursday morning. | ||
+ | * At 10 am pass change for Hall C 4-pass --> 3-pass | ||
+ | * Wednesday at noon, Hall C might swap their aerogel again; this would be an opportunity for another TAC run if needed. It was decided this is not needed. | ||
+ | |||
+ | |||
+ | = Wednesday August 17 = | ||
+ | === Past 24 hours === | ||
+ | * 9:13 am MCC starts Hall C pass change 4-pass --> 3-pass | ||
+ | * Mark Dalton accesses hall and changes 3 FCAL bases [https://logbooks.jlab.org/entry/4029733] | ||
+ | * [https://logbooks.jlab.org/entry/4029989~ 18:00 MCC calls it a night] | ||
+ | * [https://logbooks.jlab.org/entry/4030074 PD summary] | ||
+ | |||
+ | === Shift Reports === | ||
+ | * [https://logbooks.jlab.org/entry/4029759 Day shift summaries] | ||
+ | * [https://logbooks.jlab.org/entry/4029915 Swing shift summary] | ||
+ | * [ Owl shift summary] | ||
+ | * [ Early Riser shift summary] | ||
+ | {| class=wikitable | ||
+ | |+ Recorded BTA | ||
+ | |- | ||
+ | ! Shift | ||
+ | ! ABU | ||
+ | ! BANU | ||
+ | ! BNA & ACC | ||
+ | ! ER | ||
+ | |- | ||
+ | ! 8/16 Day [https://logbooks.jlab.org/entry/4029910] | ||
+ | | 0.82 h || 0.13 h || 7.05 h || 7.67 h | ||
+ | |- | ||
+ | !8/16 Swing | ||
+ | | h || h || h || h | ||
+ | |- | ||
+ | !8/17 Owl | ||
+ | | h || h || h || h | ||
+ | |- | ||
+ | |- | ||
+ | ! Total | ||
+ | | 0.82 h || 0.13 h || 7.05 h || 7.67 h | ||
+ | |} | ||
+ | |||
+ | === Reports === | ||
+ | |||
+ | === Issues === | ||
+ | |||
+ | === Plans === | ||
+ | * Continue with prodcution data on empty target through Thursday morning. | ||
+ | * Start with an amo run; then start a fresh cycle from the top. |
Latest revision as of 09:36, 17 August 2022
Back to Run Coordination Meetings:Summer2022
Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Contents
Thursday August 11
Past 24 hours
- Running on Pb target (30 nA). Another relatively good day: ABU=18.3 h for the day
- Beam down for 3.75 hrs due to afternoon thunderstorms
- Program Deputy summary
Shift Reports
- Day shift summaries (1), (2)
- Swing shift summary (1), (2)
- Owl shift summary
- Early Riser shift summary
Reports
Issues
- Continued: TAGH major link alarm. Description by shift leader. Cannot communicate with crate, but rates are fine -> we decided to run as it is (monitoring TAGH scalars with stripcharts) and have a look latter.
Plans
- Beam off all day for maintenance day
- Hall in controlled access
- Solenoid current to be lowered because of cryowork. Tim seems to be doing this from home as we speak.
- Requested survey of tagger hall for access to reset TAGH crate
- When beam restored run harp scans
- Production on Pb target.
- Next pass change (4->3) for Hall C will be Tuesday. They will be down for 6h-8h Monday to install their aerogel. Monday is auspicious for a TAC run.
Friday August 12
Past 24 hours
- Beam off Thu 630 am - ?? pm for maintenance day
- ~ 9 am access to tagger hall by Beni to reset TAGH HV crate; OK now
- ramped down solenoid for cry work (Tim)
- resume prodcution data Friday 3:18 am
Shift Reports
Reports
- Beni reset the TAGH HV crate; it's communicating again ([1])
- Malte changed 2 FCAL bases ([2], [3])
- The filter material (Molecular Sieve) Assy. for the Cryomech cold compressor in Hall-D has been completed by target group
- Tim also reports that compressor swap is complete; not sure whether that refers to the target group's work?
- Beam delivary after maintenance day delayed until ??? due to a leak in magnet LCW hose in NL.
Issues
Plans
- Continue with prodcution data on Pb through the weekend.
- Plan for TAC run on Monday, when Hall C installs their aerogel.
Monday August 15
Past 72 Hours Summary
Time lost in hall mainly due to beam tuning; Hall C bleedthrough to B is still an issue.
There is some chatter this morning about position locks [4]
Plan for Monday through Thursday
- Monday: Hall C will turn off beam at 7 am to get ready for aerogel installation at 8 am. Is supposed to take about 6 hours.
- Access to hall at 7 am to move target to empty position.
- Sasha will try to make it in by 7:30 am to start TAC measurement.
- Upon completion of TAC measurement resume production on empty target
- Hall C pass change now scheduled for Wednesday. But C now is considering changing Tuesday. Decision will be made at noon.
- Thursday 7 am end of run; start installation period for PrimeX
Friday: Day through Owl
- at 7:45 am meeting Hall B complained about bleedthrough from C; optimizing the machine led to considerable downtime during the day.
- at 12 pm MCC starts tuning
- Otherwise running on Pb target (30 nA)
Shift | ABU | BANU | BNA | ER |
---|---|---|---|---|
8/12 Day | 4.24 h | 3.3 min | 3.70 h | 8 h |
8/12 Swing | 2.97 h | 1.40 h | 3.63 h | 8 h |
8/13 Owl | 6.49 h | 0.30 h | 1.20 h | 7.93 h |
Total | 13.70 h | 1.76 h | 8.53 h | 23.93 h |
Shift Reports
Reports
- Harp scans: IHA5C11, IHA5C11B, our harp, convergence fits; looks very good, much better than scans from last night.
Issues
Plans
Saturday
Shift | ABU | BANU | BNA | ER |
---|---|---|---|---|
8/13 Day | 6.16 h | 0.14 h | 1.70 h | 7.87 h |
8/13 Swing | 4.80 h | 0.38 h | 2.82 h | 7.93 h |
8/14 Owl | 6.75 h | 0.29 h | 0.97 h | 7.9 h |
Total | 17.71 h | 0.81 h | 5.49 h | 23.70 h |
Shift Reports
Issues
- one locked up FCAL base; shift crew followed reset procedure
Sunday
Shift | ABU | BANU | BNA | ER |
---|---|---|---|---|
8/14 Day [5] | 6.46 h | 0.21 h | 1.33 h | 7.82 h |
8/14 Swing [6] | 5.62 h | 0.39 h | 2.00 h | 7.95 h |
8/15 Owl [7] | 6.24 h | 0.46 h | 1.30 h | 7.58 h |
Total | 18.32 h | 1.06 h | 4.63 h | 23.35 h |
Shift reports
- Day shift summary
- Swing shift summary
- Owl shift summary
- Early Riser shift summary
Tuesday August 16
Past 24 hours
- We did a TAC run while Hall C was installing their aerogel
- Otherwise production running on empty target
Shift Reports
Shift | ABU | BANU | BNA | ER |
---|---|---|---|---|
8/15 Day [8] | 6.15 h | 0.78 h | 1.07 h | 8.0 h |
8/15 Swing [9] | 5.89 h | 0.36 h | 1.75 h | 7.77 h |
8/16 Owl [10] | 3.98 h | 0.12 h | 3.90 h | 7.88 h |
Total | h | h | h | h |
Reports
Issues
- Excursions of AC.y beam position still ongoing, but less frequent
- The acceptable tolerance in 0.2 mm from nominal; so, most of these blips are to far.
Plans
- Continue with prodcution data on empty target through Thursday morning.
- At 10 am pass change for Hall C 4-pass --> 3-pass
- Wednesday at noon, Hall C might swap their aerogel again; this would be an opportunity for another TAC run if needed. It was decided this is not needed.
Wednesday August 17
Past 24 hours
- 9:13 am MCC starts Hall C pass change 4-pass --> 3-pass
- Mark Dalton accesses hall and changes 3 FCAL bases [11]
- 18:00 MCC calls it a night
- PD summary
Shift Reports
- Day shift summaries
- Swing shift summary
- [ Owl shift summary]
- [ Early Riser shift summary]
Shift | ABU | BANU | BNA & ACC | ER |
---|---|---|---|---|
8/16 Day [12] | 0.82 h | 0.13 h | 7.05 h | 7.67 h |
8/16 Swing | h | h | h | h |
8/17 Owl | h | h | h | h |
Total | 0.82 h | 0.13 h | 7.05 h | 7.67 h |
Reports
Issues
Plans
- Continue with prodcution data on empty target through Thursday morning.
- Start with an amo run; then start a fresh cycle from the top.