Difference between revisions of "September 09, 2021 CPP Design Meeting"
From GlueXWiki
(→Minutes and Action Items) |
|||
(2 intermediate revisions by the same user not shown) | |||
Line 12: | Line 12: | ||
*** Lead absorbers - drawings in review | *** Lead absorbers - drawings in review | ||
*** assembly components - drawings in review | *** assembly components - drawings in review | ||
− | ** Stand All parts here - to be assembled in the TEDF High bay] | + | ** Stand All parts here - to be assembled in the TEDF High bay [[image:cpp_stand_1.jpg|thumb]] [[image:cpp_stand_2.jpg|thumb]] [[image:cpp_stand_3.jpg|thumb]] |
** Steel - all received [[image:cpp_steel_3.jpg|thumb]] | ** Steel - all received [[image:cpp_steel_3.jpg|thumb]] | ||
** Fcal platform mods | ** Fcal platform mods | ||
Line 29: | Line 29: | ||
== Minutes and Action Items == | == Minutes and Action Items == | ||
− | + | * Rory to bring 4 more chambers to JLAB end of Sept | |
+ | * Discussed microscope move - no new info | ||
+ | * Plan to stack 2 chambers in EEL to check efficiency for the review recommendation | ||
+ | * A second scintillator was added to the test setup | ||
+ | * Elton and Albert are looking at the data | ||
==Action Items == | ==Action Items == |
Latest revision as of 14:01, 21 October 2021
Meeting Time and Place
Thursday August 26, 2021, 3:00pm Bluejeans https://bluejeans.com/465620466
- Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark I
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/August_26,_2021_CPP_Design_Meeting
- Testing status - Beni
- Design/Fab/Procurement status
- Installation/assy 3D Model and dwgs
- Lead absorbers - drawings in review
- assembly components - drawings in review
- Stand All parts here - to be assembled in the TEDF High bay
- Steel - all received
- Fcal platform mods
- Cutouts complete
- Floor Rails installed and aligned
- Installation/assy 3D Model and dwgs
- Things to work out
- Gas system, manifold/bubblers (Beni has some)
- Complete structural analysis - approved by Tom Renzo - need to release into system
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
- Modified US vacuum system
- Solid target installation
- Installation drawing including Microscope move
- CPP Detector operations in Hall D OSP
- Possible use of nitrogen flow for cooling electronics in Faraday cage
Minutes and Action Items
- Rory to bring 4 more chambers to JLAB end of Sept
- Discussed microscope move - no new info
- Plan to stack 2 chambers in EEL to check efficiency for the review recommendation
- A second scintillator was added to the test setup
- Elton and Albert are looking at the data