(Created page with "== Meeting Time and Place == Thursday Jun 03, 2021, 3:30pm Bluejeans https://bluejeans.com/465620466 * Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark...") |
(→Minutes and Action Items) |
||
(5 intermediate revisions by the same user not shown) | |||
Line 28: | Line 28: | ||
== Minutes and Action Items == | == Minutes and Action Items == | ||
+ | * Beni working testing OSP to be re-issued with more detail | ||
+ | * Beni will start without a nitrogen purge in the Faraday cage to see what happens. | ||
+ | * Meeting with Elton and Nick tomorrow in Hall to discuss cable routings | ||
+ | * Gas system in EEL almost ready for leak check | ||
+ | * Rory will be bringing the 4 MWPCs next week Wednesday, 9am | ||
+ | * Rory said to keep plastic covering center hole | ||
+ | * Will need 2-3 people w/respirators to unload from truck | ||
+ | * Rory will have 2 lifting bars attached for us to handle the chambers | ||
+ | * We will send foam pads back to UMASS | ||
+ | * Tim to send cell phone #s to Rory | ||
+ | * Support structure due in next week | ||
+ | * Steel procurement has been awarded |
Latest revision as of 08:40, 17 June 2021
Meeting Time and Place
Thursday Jun 03, 2021, 3:30pm Bluejeans https://bluejeans.com/465620466
- Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark I
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/June_03,_2021_CPP_Design_Meeting
- Plan for bringing/checking chambers from UMASS
- OSP status - Beni
- Gas system status - Tim
- Chamber status - Rory
- Unloading plan - Mark
- Nitrogen purge desired on electronics volume
- Cable routings
- Design/Fab/Procurement status
- Stand
- Steel
- Fcal platform mods
- Things to work out
- Gas system, manifold/bubblers (Beni has some)
- Complete structural analysis
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
- Modified US vacuum system
- Solid target installation
- Installation drawing including Microscope move
Minutes and Action Items
- Beni working testing OSP to be re-issued with more detail
- Beni will start without a nitrogen purge in the Faraday cage to see what happens.
- Meeting with Elton and Nick tomorrow in Hall to discuss cable routings
- Gas system in EEL almost ready for leak check
- Rory will be bringing the 4 MWPCs next week Wednesday, 9am
- Rory said to keep plastic covering center hole
- Will need 2-3 people w/respirators to unload from truck
- Rory will have 2 lifting bars attached for us to handle the chambers
- We will send foam pads back to UMASS
- Tim to send cell phone #s to Rory
- Support structure due in next week
- Steel procurement has been awarded